BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Built-in wardrobe, installed: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦99,421per m²

Tender rate about ₦132,702 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for built-in wardrobe, installed is ₦99,421 per m² in Abuja: ₦95,000 materials, ₦4,421 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦132,702 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialBuilt-in wardrobe (MDF/laminate), per m2 face1 m²-₦95,000₦95,000
Labour (hours)Joiner / cabinet maker1.5 h-₦2,948₦4,421
Materials₦95,000
Labour₦4,421
Plant₦0
Net unit rate per m²₦99,421

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦99,421₦132,702
Lagos₦105,475₦140,782
Port Harcourt₦106,800₦142,551
Ibadan₦93,787₦125,182
Osogbo (Osun)₦94,516₦126,155
Kano₦91,666₦122,351
Kaduna₦92,749₦123,796
Enugu₦96,637₦128,986
Benin City₦97,675₦130,372
Uyo₦101,608₦135,621
Jos₦93,699₦125,064
Riverine / creek site₦128,363₦171,333

Related doors & windows rates

Frequently asked questions

How much does built-in wardrobe, installed cost per m² in Nigeria?

About ₦99,421 per m² net in Abuja as at 15 October 2026, or about ₦132,702 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦105,475 per m² and the tender rate about ₦140,782 per m².

What does the rate include?

Materials (Built-in wardrobe (MDF/laminate)) with waste allowances; labour (Joiner / cabinet maker) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/j13-built-in-wardrobe-installed/, prices as at 15 October 2026.