Prices as at 15 October 2026, checked weekly. Base location Abuja.

Frameless 12mm tempered glass door, s&f: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦180,344per m²

Tender rate about ₦240,713 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for frameless 12mm tempered glass door, s&f is ₦180,344 per m² in Abuja: ₦180,000 materials, ₦344 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦240,713 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialFrameless 12mm tempered glass door with patch fittings - supply & fix1 m²-₦180,000₦180,000
Labour (hours)Unskilled labourer0.3 h-₦1,146₦344
Materials₦180,000
Labour₦344
Plant₦0
Net unit rate per m²₦180,344

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦180,344₦240,713
Lagos₦191,171₦255,165
Port Harcourt₦194,727₦259,911
Ibadan₦171,275₦228,609
Osogbo (Osun)₦173,058₦230,988
Kano₦167,658₦223,781
Kaduna₦169,468₦226,197
Enugu₦176,675₦235,817
Benin City₦178,482₦238,228
Uyo₦185,692₦247,852
Jos₦171,268₦228,600
Riverine / creek site₦234,378₦312,836

Related doors & windows rates

Frequently asked questions

How much does frameless 12mm tempered glass door, s&f cost per m² in Nigeria?

About ₦180,344 per m² net in Abuja as at 15 October 2026, or about ₦240,713 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦191,171 per m² and the tender rate about ₦255,165 per m².

What does the rate include?

Materials (Frameless 12mm tempered glass door with patch fittings - supply & fix) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.