BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Steel sliding/swing gate, fabricated & installed: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦88,037per m²

Tender rate about ₦117,507 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for steel sliding/swing gate, fabricated & installed is ₦88,037 per m² in Abuja: ₦86,236 materials, ₦1,801 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦117,507 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialFabricated steel gate (sliding/swing), primed & painted1 m²-₦85,000₦85,000
MaterialOPC 42.5 cement, 50kg bag - adopted market average0.1 bag3%₦12,000₦1,236
Labour (hours)Mason / bricklayer0.5 h-₦2,456₦1,228
Labour (hours)Unskilled labourer0.5 h-₦1,146₦573
Materials₦86,236
Labour₦1,801
Plant₦0
Net unit rate per m²₦88,037

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦88,037₦117,507
Lagos₦93,356₦124,606
Port Harcourt₦94,846₦126,595
Ibadan₦83,365₦111,271
Osogbo (Osun)₦84,137₦112,302
Kano₦81,550₦108,849
Kaduna₦82,467₦110,072
Enugu₦85,952₦114,725
Benin City₦86,851₦115,924
Uyo₦90,354₦120,600
Jos₦83,329₦111,223
Riverine / creek site₦114,088₦152,279

Related doors & windows rates

Frequently asked questions

How much does steel sliding/swing gate, fabricated & installed cost per m² in Nigeria?

About ₦88,037 per m² net in Abuja as at 15 October 2026, or about ₦117,507 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦93,356 per m² and the tender rate about ₦124,606 per m².

What does the rate include?

Materials (Fabricated steel gate (sliding/swing), OPC 42.5 cement) with waste allowances; labour (Mason / bricklayer, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/j14-steel-sliding-swing-gate-fabricated-and-installed/, prices as at 15 October 2026.