BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

WC suite (mid-range), supplied, fixed & connected: cost per unit in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦142,805per unit

Tender rate about ₦190,609 per unit with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for wC suite (mid-range), supplied, fixed & connected is ₦142,805 per unit in Abuja: ₦132,980 materials, ₦9,825 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦190,609 per unit.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialWC suite, close-coupled, mid-range1 unit-₦125,000₦125,000
MaterialPPR pipe 20mm, 4m0.5 length5%₦3,800₦1,995
MaterialuPVC soil pipe 110mm, 5.8m0.3 length5%₦19,000₦5,985
Labour (hours)Plumber3 h-₦2,784₦8,351
Labour (hours)Plumber's mate1 h-₦1,474₦1,474
Materials₦132,980
Labour₦9,825
Plant₦0
Net unit rate per unit₦142,805

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per unitTender rate incl. OH&P and VAT
Abuja (FCT)₦142,805₦190,609
Lagos₦151,570₦202,307
Port Harcourt₦152,952₦204,152
Ibadan₦134,191₦179,111
Osogbo (Osun)₦135,030₦180,230
Kano₦131,040₦174,905
Kaduna₦132,665₦177,074
Enugu₦138,180₦184,436
Benin City₦139,707₦186,473
Uyo₦145,321₦193,966
Jos₦133,994₦178,849
Riverine / creek site₦183,682₦245,168

Related plumbing rates

Frequently asked questions

How much does wC suite (mid-range), supplied, fixed & connected cost per unit in Nigeria?

About ₦142,805 per unit net in Abuja as at 15 October 2026, or about ₦190,609 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦151,570 per unit and the tender rate about ₦202,307 per unit.

What does the rate include?

Materials (PPR pipe 20mm, WC suite, uPVC soil pipe 110mm) with waste allowances; labour (Plumber, Plumber's mate) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/f03-wc-suite-mid-range-supplied-fixed-and-connected/, prices as at 15 October 2026.