Hot water point, 25mm PPR (avg 6m run): cost per point in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦19,579per point

Tender rate about ₦26,134 per point with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for hot water point, 25mm PPR (avg 6m run) is ₦19,579 per point in Abuja: ₦15,240 materials, ₦4,339 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦26,134 per point.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialPPR pipe 25mm, 4m1.6 length5%₦5,500₦9,240
MaterialPPR fittings allowance, per water point1 set-₦6,000₦6,000
Labour (hours)Plumber1.4 h-₦2,784₦3,897
Labour (hours)Plumber's mate0.3 h-₦1,474₦442
Materials₦15,240
Labour₦4,339
Plant₦0
Net unit rate per point₦19,579

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per pointTender rate incl. OH&P and VAT
Abuja (FCT)₦19,579₦26,134
Lagos₦20,841₦27,817
Port Harcourt₦20,582₦27,471
Ibadan₦17,950₦23,958
Osogbo (Osun)₦17,885₦23,872
Kano₦17,428₦23,262
Kaduna₦17,710₦23,639
Enugu₦18,407₦24,568
Benin City₦18,646₦24,888
Uyo₦19,386₦25,875
Jos₦17,863₦23,842
Riverine / creek site₦24,585₦32,815

Related plumbing rates

Frequently asked questions

How much does hot water point, 25mm PPR (avg 6m run) cost per point in Nigeria?

About ₦19,579 per point net in Abuja as at 15 October 2026, or about ₦26,134 per point as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦20,841 per point and the tender rate about ₦27,817 per point.

What does the rate include?

Materials (PPR fittings allowance, PPR pipe 25mm) with waste allowances; labour (Plumber, Plumber's mate) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.