Prices as at 15 October 2026, checked weekly. Base location Abuja.

Soil & waste point, uPVC 110/50mm: cost per point in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦25,300per point

Tender rate about ₦33,769 per point with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for soil & waste point, uPVC 110/50mm is ₦25,300 per point in Abuja: ₦20,388 materials, ₦4,912 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦33,769 per point.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialuPVC soil pipe 110mm, 5.8m0.5 length5%₦19,000₦9,975
MaterialuPVC waste pipe 50mm, 5.8m0.5 length5%₦6,500₦3,412
MaterialuPVC 110mm bend/junction2 unit-₦3,500₦7,000
Labour (hours)Plumber1.5 h-₦2,784₦4,176
Labour (hours)Plumber's mate0.5 h-₦1,474₦737
Materials₦20,388
Labour₦4,912
Plant₦0
Net unit rate per point₦25,300

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per pointTender rate incl. OH&P and VAT
Abuja (FCT)₦25,300₦33,769
Lagos₦26,916₦35,926
Port Harcourt₦26,685₦35,618
Ibadan₦23,298₦31,097
Osogbo (Osun)₦23,256₦31,041
Kano₦22,645₦30,225
Kaduna₦22,996₦30,694
Enugu₦23,910₦31,913
Benin City₦24,212₦32,317
Uyo₦25,175₦33,602
Jos₦23,200₦30,966
Riverine / creek site₦31,908₦42,588

Related plumbing rates

Frequently asked questions

How much does soil & waste point, uPVC 110/50mm cost per point in Nigeria?

About ₦25,300 per point net in Abuja as at 15 October 2026, or about ₦33,769 per point as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦26,916 per point and the tender rate about ₦35,926 per point.

What does the rate include?

Materials (uPVC 110mm bend/junction, uPVC soil pipe 110mm, uPVC waste pipe 50mm) with waste allowances; labour (Plumber, Plumber's mate) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/f14-soil-and-waste-point-upvc-110-50mm/, prices as at 15 October 2026.