BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Acrylic bathtub 1.7m with mixer, fixed & connected: cost per unit in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦302,904per unit

Tender rate about ₦404,300 per unit with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for acrylic bathtub 1.7m with mixer, fixed & connected is ₦302,904 per unit in Abuja: ₦286,038 materials, ₦16,866 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦404,300 per unit.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialAcrylic bathtub 1.7m with mixer1 unit-₦280,000₦280,000
MaterialPPR pipe 20mm, 4m1 length5%₦3,800₦3,990
MaterialuPVC waste pipe 50mm, 5.8m0.3 length5%₦6,500₦2,048
Labour (hours)Plumber5 h-₦2,784₦13,919
Labour (hours)Plumber's mate2 h-₦1,474₦2,948
Materials₦286,038
Labour₦16,866
Plant₦0
Net unit rate per unit₦302,904

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per unitTender rate incl. OH&P and VAT
Abuja (FCT)₦302,904₦404,300
Lagos₦321,415₦429,008
Port Harcourt₦324,943₦433,717
Ibadan₦285,229₦380,708
Osogbo (Osun)₦287,246₦383,400
Kano₦278,665₦371,947
Kaduna₦282,031₦376,440
Enugu₦293,810₦392,162
Benin City₦297,007₦396,430
Uyo₦308,955₦412,377
Jos₦284,891₦380,258
Riverine / creek site₦390,402₦521,087

Related plumbing rates

Frequently asked questions

How much does acrylic bathtub 1.7m with mixer, fixed & connected cost per unit in Nigeria?

About ₦302,904 per unit net in Abuja as at 15 October 2026, or about ₦404,300 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦321,415 per unit and the tender rate about ₦429,008 per unit.

What does the rate include?

Materials (Acrylic bathtub 1.7m with mixer, PPR pipe 20mm, uPVC waste pipe 50mm) with waste allowances; labour (Plumber, Plumber's mate) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/f08-acrylic-bathtub-1-7m-with-mixer-fixed-and-connected/, prices as at 15 October 2026.