Prices as at 15 October 2026, checked weekly. Base location Abuja.

WC one-piece (premium), supplied, fixed & connected: cost per unit in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦369,197per unit

Tender rate about ₦492,784 per unit with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for wC one-piece (premium), supplied, fixed & connected is ₦369,197 per unit in Abuja: ₦357,980 materials, ₦11,217 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦492,784 per unit.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialWC one-piece, premium1 unit-₦350,000₦350,000
MaterialPPR pipe 20mm, 4m0.5 length5%₦3,800₦1,995
MaterialuPVC soil pipe 110mm, 5.8m0.3 length5%₦19,000₦5,985
Labour (hours)Plumber3.5 h-₦2,784₦9,743
Labour (hours)Plumber's mate1 h-₦1,474₦1,474
Materials₦357,980
Labour₦11,217
Plant₦0
Net unit rate per unit₦369,197

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per unitTender rate incl. OH&P and VAT
Abuja (FCT)₦369,197₦492,784
Lagos₦391,573₦522,651
Port Harcourt₦397,274₦530,261
Ibadan₦349,054₦465,899
Osogbo (Osun)₦352,073₦469,929
Kano₦341,334₦455,595
Kaduna₦345,250₦460,822
Enugu₦359,794₦480,234
Benin City₦363,598₦485,311
Uyo₦378,254₦504,873
Jos₦348,830₦465,600
Riverine / creek site₦477,713₦637,625

Related plumbing rates

Frequently asked questions

How much does wC one-piece (premium), supplied, fixed & connected cost per unit in Nigeria?

About ₦369,197 per unit net in Abuja as at 15 October 2026, or about ₦492,784 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦391,573 per unit and the tender rate about ₦522,651 per unit.

What does the rate include?

Materials (PPR pipe 20mm, WC one-piece, uPVC soil pipe 110mm) with waste allowances; labour (Plumber, Plumber's mate) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/f07-wc-one-piece-premium-supplied-fixed-and-connected/, prices as at 15 October 2026.