BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Cold water point, 20mm PPR (avg 6m run): cost per point in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦16,167per point

Tender rate about ₦21,578 per point with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for cold water point, 20mm PPR (avg 6m run) is ₦16,167 per point in Abuja: ₦12,384 materials, ₦3,783 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦21,578 per point.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialPPR pipe 20mm, 4m1.6 length5%₦3,800₦6,384
MaterialPPR fittings allowance, per water point1 set-₦6,000₦6,000
Labour (hours)Plumber1.2 h-₦2,784₦3,340
Labour (hours)Plumber's mate0.3 h-₦1,474₦442
Materials₦12,384
Labour₦3,783
Plant₦0
Net unit rate per point₦16,167

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per pointTender rate incl. OH&P and VAT
Abuja (FCT)₦16,167₦21,578
Lagos₦17,212₦22,974
Port Harcourt₦16,968₦22,648
Ibadan₦14,791₦19,742
Osogbo (Osun)₦14,726₦19,655
Kano₦14,354₦19,159
Kaduna₦14,591₦19,476
Enugu₦15,162₦20,238
Benin City₦15,362₦20,504
Uyo₦15,971₦21,317
Jos₦14,715₦19,641
Riverine / creek site₦20,260₦27,042

Related plumbing rates

Frequently asked questions

How much does cold water point, 20mm PPR (avg 6m run) cost per point in Nigeria?

About ₦16,167 per point net in Abuja as at 15 October 2026, or about ₦21,578 per point as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦17,212 per point and the tender rate about ₦22,974 per point.

What does the rate include?

Materials (PPR fittings allowance, PPR pipe 20mm) with waste allowances; labour (Plumber, Plumber's mate) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/f12-cold-water-point-20mm-ppr-avg-6m-run/, prices as at 15 October 2026.