BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Borehole drilling in basement rock, Abuja (subcontract): cost per m in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦22,000per m

Tender rate about ₦29,364 per m with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for borehole drilling in basement rock, Abuja (subcontract) is ₦22,000 per m in Abuja: ₦22,000 materials, ₦0 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦29,364 per m.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialBorehole drilling, Abuja basement rock, per m (subcontract)1 m-₦22,000₦22,000
Materials₦22,000
Labour₦0
Plant₦0
Net unit rate per m₦22,000

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per mTender rate incl. OH&P and VAT
Abuja (FCT)₦22,000₦29,364
Lagos₦23,320₦31,126
Port Harcourt₦23,760₦31,714
Ibadan₦20,900₦27,896
Osogbo (Osun)₦21,120₦28,190
Kano₦20,460₦27,309
Kaduna₦20,680₦27,603
Enugu₦21,560₦28,777
Benin City₦21,780₦29,071
Uyo₦22,660₦30,245
Jos₦20,900₦27,896
Riverine / creek site₦28,600₦38,174

Related plumbing rates

Frequently asked questions

How much does borehole drilling in basement rock, Abuja (subcontract) cost per m in Nigeria?

About ₦22,000 per m net in Abuja as at 15 October 2026, or about ₦29,364 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦23,320 per m and the tender rate about ₦31,126 per m.

What does the rate include?

Materials (Borehole drilling) with waste allowances; labour (no labour) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/f17-borehole-drilling-in-basement-rock-abuja-subcontract/, prices as at 15 October 2026.