Laterite sub-base, spread & compacted in layers (compacted volume): cost per m³ in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦13,628per m³

Tender rate about ₦18,189 per m³ with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for laterite sub-base, spread & compacted in layers (compacted volume) is ₦13,628 per m³ in Abuja: ₦9,896 materials, ₦229 labour and ₦3,502 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦18,189 per m³.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialLaterite, per tonne2.1 tonne5%₦4,250₦9,371
MaterialWater, per m30.15 m³-₦3,500₦525
Plant (days)Motor grader (CAT 140 class)0.0025 day-₦729,900₦1,825
Plant (days)Vibratory roller 10-12t0.002 day-₦477,310₦955
Plant (days)Water tanker 10,000L0.002 day-₦361,330₦723
Labour (hours)Unskilled labourer0.2 h-₦1,146₦229
Materials₦9,896
Labour₦229
Plant₦3,502
Net unit rate per m³₦13,628

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m³Tender rate incl. OH&P and VAT
Abuja (FCT)₦13,628₦18,189
Lagos₦14,415₦19,240
Port Harcourt₦14,688₦19,605
Ibadan₦12,912₦17,234
Osogbo (Osun)₦13,069₦17,444
Kano₦12,702₦16,954
Kaduna₦12,808₦17,096
Enugu₦13,314₦17,770
Benin City₦13,487₦18,002
Uyo₦13,995₦18,680
Jos₦12,977₦17,321
Riverine / creek site₦18,020₦24,052

Related roads & external rates

Frequently asked questions

How much does laterite sub-base, spread & compacted in layers (compacted volume) cost per m³ in Nigeria?

About ₦13,628 per m³ net in Abuja as at 15 October 2026, or about ₦18,189 per m³ as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦14,415 per m³ and the tender rate about ₦19,240 per m³.

What does the rate include?

Materials (Laterite, Water) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Motor grader (CAT 140 class), Vibratory roller 10-12t, Water tanker 10,000L) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.