900mm precast culvert pipe laid with 1:3:6 surround: cost per m in Nigeria
Net unit rate in Abuja, excluding overheads, profit and VAT
₦214,035per m
Tender rate about ₦285,682 per m with overheads, contingency, profit and VAT.
Price a BoQ with this rateAs at 15 October 2026, the net unit rate for 900mm precast culvert pipe laid with 1:3:6 surround is ₦214,035 per m in Abuja: ₦187,443 materials, ₦5,895 labour and ₦20,696 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦285,682 per m.
Rate build-up (Abuja, Oct 2026)
| Resource type | Resource | Quantity per unit | Waste | Rate | Cost |
|---|---|---|---|---|---|
| Material | Concrete culvert pipe 900mm dia, per m | 1 m | 2% | ₦150,000 | ₦153,000 |
| Material | OPC 42.5 cement, 50kg bag - adopted market average | 1.76 bag | 3% | ₦12,000 | ₦21,754 |
| Material | Sharp sand, per tonne | 0.3 tonne | 8% | ₦6,500 | ₦2,106 |
| Material | Granite 3/4", per tonne | 0.56 tonne | 5% | ₦18,000 | ₦10,584 |
| Plant (days) | Hydraulic excavator 20-22t (CAT 320/215 class) | 0.025 day | - | ₦827,850 | ₦20,696 |
| Labour (hours) | Mason / bricklayer | 1 h | - | ₦2,456 | ₦2,456 |
| Labour (hours) | Unskilled labourer | 3 h | - | ₦1,146 | ₦3,439 |
| Materials | ₦187,443 | ||||
| Labour | ₦5,895 | ||||
| Plant | ₦20,696 | ||||
| Net unit rate per m | ₦214,035 |
Rate by location
Materials, labour and plant are adjusted separately with Buildocrat's location factors.
| Location | Net rate per m | Tender rate incl. OH&P and VAT |
|---|---|---|
| Abuja (FCT) | ₦214,035 | ₦285,682 |
| Lagos | ₦226,788 | ₦302,704 |
| Port Harcourt | ₦230,391 | ₦307,514 |
| Ibadan | ₦202,449 | ₦270,218 |
| Osogbo (Osun) | ₦204,442 | ₦272,879 |
| Kano | ₦198,405 | ₦264,821 |
| Kaduna | ₦200,456 | ₦267,559 |
| Enugu | ₦208,693 | ₦278,552 |
| Benin City | ₦211,099 | ₦281,764 |
| Uyo | ₦219,395 | ₦292,836 |
| Jos | ₦202,745 | ₦270,613 |
| Riverine / creek site | ₦279,136 | ₦372,576 |
Related roads & external rates
- R01 Scarify, water & compact subgrade to 95% MDD₦577 per m²
- R02 Laterite sub-base, spread & compacted in layers (compacted volume)₦13,628 per m³
- R03 Crushed stone base course, compacted (compacted volume)₦34,642 per m³
- R04 Prime coat MC-30 at 1.0 L/m2₦1,653 per m²
- R05 Tack coat (emulsion) at 0.3 L/m2₦420 per m²
- R06 Asphalt wearing course 50mm, laid & compacted₦20,481 per m²
- R07 Asphalt binder course 60mm, laid & compacted₦23,291 per m²
- R08 Precast road kerb 900x300x150 on concrete bed & haunch₦17,408 per m
- R09 Precast 600mm U-drain with cover, laid on concrete bed₦67,702 per m
- R10 In-situ RC drain 600x600 internal, 150mm walls & base, incl. excavation, formwork & rebar₦102,171 per m
- R12 Thermoplastic road marking, 100mm line₦711 per m
- G01 60mm interlocking paving on 50mm sand bed, compacted₦11,169 per m²
- G02 80mm interlocking paving on 50mm sand bed, compacted₦13,390 per m²
- R13 Chain-link fence 1.8m on angle posts @3m with 3 lines barbed wire₦12,743 per m
- R14 225mm block fence wall 2.4m high incl. foundation, piers, plaster both sides & razor wire₦83,156 per m
- R16 Carpet grass laid on 100mm topsoil, watered₦2,790 per m²
- R17 Cement-stabilised base 150mm (5% cement) mixed in place and compacted₦6,657 per m²
- R18 Double surface dressing with emulsion and 10/14mm chippings₦3,918 per m²
Frequently asked questions
How much does 900mm precast culvert pipe laid with 1:3:6 surround cost per m in Nigeria?
About ₦214,035 per m net in Abuja as at 15 October 2026, or about ₦285,682 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).
What is the rate in Lagos?
Applying Buildocrat's Lagos location factors, the net rate is about ₦226,788 per m and the tender rate about ₦302,704 per m.
What does the rate include?
Materials (Concrete culvert pipe 900mm dia, Granite 3/4", OPC 42.5 cement, Sharp sand) with waste allowances; labour (Mason / bricklayer, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Hydraulic excavator 20-22t (CAT 320/215 class)) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.
How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/r11-900mm-precast-culvert-pipe-laid-with-1-3-6-surround/, prices as at 15 October 2026.