Cement-stabilised base 150mm (5% cement) mixed in place and compacted: cost per m² in Nigeria
Net unit rate in Abuja, excluding overheads, profit and VAT
₦6,657per m²
Tender rate about ₦8,886 per m² with overheads, contingency, profit and VAT.
Price a BoQ with this rateAs at 15 October 2026, the net unit rate for cement-stabilised base 150mm (5% cement) mixed in place and compacted is ₦6,657 per m² in Abuja: ₦5,181 materials, ₦34.39 labour and ₦1,442 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦8,886 per m².
Rate build-up (Abuja, Oct 2026)
| Resource type | Resource | Quantity per unit | Waste | Rate | Cost |
|---|---|---|---|---|---|
| Material | OPC 42.5 cement, 50kg bag - adopted market average | 0.3 bag | 3% | ₦12,000 | ₦3,708 |
| Material | Laterite, per tonne | 0.33 tonne | 5% | ₦4,250 | ₦1,473 |
| Plant (days) | Soil stabiliser / recycler | 0.000286 day | - | ₦3,252,700 | ₦930 |
| Plant (days) | Motor grader (CAT 140 class) | 0.000286 day | - | ₦729,900 | ₦209 |
| Plant (days) | Vibratory roller 16-20t | 0.000333 day | - | ₦639,020 | ₦213 |
| Plant (days) | Water tanker 10,000L | 0.00025 day | - | ₦361,330 | ₦90.33 |
| Labour (hours) | Unskilled labourer | 0.03 h | - | ₦1,146 | ₦34.39 |
| Materials | ₦5,181 | ||||
| Labour | ₦34.39 | ||||
| Plant | ₦1,442 | ||||
| Net unit rate per m² | ₦6,657 |
Rate by location
Materials, labour and plant are adjusted separately with Buildocrat's location factors.
| Location | Net rate per m² | Tender rate incl. OH&P and VAT |
|---|---|---|
| Abuja (FCT) | ₦6,657 | ₦8,886 |
| Lagos | ₦7,043 | ₦9,400 |
| Port Harcourt | ₦7,185 | ₦9,591 |
| Ibadan | ₦6,319 | ₦8,434 |
| Osogbo (Osun) | ₦6,398 | ₦8,540 |
| Kano | ₦6,214 | ₦8,294 |
| Kaduna | ₦6,267 | ₦8,364 |
| Enugu | ₦6,518 | ₦8,700 |
| Benin City | ₦6,599 | ₦8,808 |
| Uyo | ₦6,851 | ₦9,144 |
| Jos | ₦6,347 | ₦8,472 |
| Riverine / creek site | ₦8,792 | ₦11,735 |
Related roads & external rates
- R01 Scarify, water & compact subgrade to 95% MDD₦577 per m²
- R02 Laterite sub-base, spread & compacted in layers (compacted volume)₦13,628 per m³
- R03 Crushed stone base course, compacted (compacted volume)₦34,642 per m³
- R04 Prime coat MC-30 at 1.0 L/m2₦1,653 per m²
- R05 Tack coat (emulsion) at 0.3 L/m2₦420 per m²
- R06 Asphalt wearing course 50mm, laid & compacted₦20,481 per m²
- R07 Asphalt binder course 60mm, laid & compacted₦23,291 per m²
- R08 Precast road kerb 900x300x150 on concrete bed & haunch₦17,408 per m
- R09 Precast 600mm U-drain with cover, laid on concrete bed₦67,702 per m
- R10 In-situ RC drain 600x600 internal, 150mm walls & base, incl. excavation, formwork & rebar₦102,171 per m
- R11 900mm precast culvert pipe laid with 1:3:6 surround₦214,035 per m
- R12 Thermoplastic road marking, 100mm line₦711 per m
- G01 60mm interlocking paving on 50mm sand bed, compacted₦11,169 per m²
- G02 80mm interlocking paving on 50mm sand bed, compacted₦13,390 per m²
- R13 Chain-link fence 1.8m on angle posts @3m with 3 lines barbed wire₦12,743 per m
- R14 225mm block fence wall 2.4m high incl. foundation, piers, plaster both sides & razor wire₦83,156 per m
- R16 Carpet grass laid on 100mm topsoil, watered₦2,790 per m²
- R18 Double surface dressing with emulsion and 10/14mm chippings₦3,918 per m²
Frequently asked questions
How much does cement-stabilised base 150mm (5% cement) mixed in place and compacted cost per m² in Nigeria?
About ₦6,657 per m² net in Abuja as at 15 October 2026, or about ₦8,886 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).
What is the rate in Lagos?
Applying Buildocrat's Lagos location factors, the net rate is about ₦7,043 per m² and the tender rate about ₦9,400 per m².
What does the rate include?
Materials (Laterite, OPC 42.5 cement) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Motor grader (CAT 140 class), Soil stabiliser / recycler, Vibratory roller 16-20t, Water tanker 10,000L) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.
How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/r17-cement-stabilised-base-150mm-5-cement-mixed-in-place-and/, prices as at 15 October 2026.