Prices as at 15 October 2026, checked weekly. Base location Abuja.

Crushed stone base course, compacted (compacted volume): cost per m³ in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦34,642per m³

Tender rate about ₦46,239 per m³ with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for crushed stone base course, compacted (compacted volume) is ₦34,642 per m³ in Abuja: ₦30,608 materials, ₦287 labour and ₦3,748 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦46,239 per m³.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialCrushed stone base 0/40 (graded), per tonne2.3 tonne5%₦12,500₦30,188
MaterialWater, per m30.12 m³-₦3,500₦420
Plant (days)Motor grader (CAT 140 class)0.002857 day-₦729,900₦2,085
Plant (days)Vibratory roller 10-12t0.002222 day-₦477,310₦1,061
Plant (days)Water tanker 10,000L0.001667 day-₦361,330₦602
Labour (hours)Unskilled labourer0.25 h-₦1,146₦287
Materials₦30,608
Labour₦287
Plant₦3,748
Net unit rate per m³₦34,642

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m³Tender rate incl. OH&P and VAT
Abuja (FCT)₦34,642₦46,239
Lagos₦36,689₦48,971
Port Harcourt₦37,376₦49,888
Ibadan₦32,867₦43,869
Osogbo (Osun)₦33,234₦44,359
Kano₦32,241₦43,033
Kaduna₦32,555₦43,453
Enugu₦33,898₦45,245
Benin City₦34,285₦45,761
Uyo₦35,630₦47,557
Jos₦32,936₦43,962
Riverine / creek site₦45,353₦60,534

Related roads & external rates

Frequently asked questions

How much does crushed stone base course, compacted (compacted volume) cost per m³ in Nigeria?

About ₦34,642 per m³ net in Abuja as at 15 October 2026, or about ₦46,239 per m³ as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦36,689 per m³ and the tender rate about ₦48,971 per m³.

What does the rate include?

Materials (Crushed stone base 0/40 (graded), Water) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Motor grader (CAT 140 class), Vibratory roller 10-12t, Water tanker 10,000L) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/r03-crushed-stone-base-course-compacted-compacted-volume/, prices as at 15 October 2026.