BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

In-situ RC drain 600x600 internal, 150mm walls & base, incl. excavation, formwork & rebar: cost per m in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦102,171per m

Tender rate about ₦136,372 per m with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for in-situ RC drain 600x600 internal, 150mm walls & base, incl. excavation, formwork & rebar is ₦102,171 per m in Abuja: ₦80,967 materials, ₦19,306 labour and ₦1,898 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦136,372 per m.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialOPC 42.5 cement, 50kg bag - adopted market average2.22 bag3%₦12,000₦27,439
MaterialSharp sand, per tonne0.25 tonne8%₦6,500₦1,755
MaterialGranite 3/4", per tonne0.48 tonne5%₦18,000₦9,072
MaterialHigh-yield rebar 12-16mm, per tonne0.03 tonne5%₦1,050,000₦33,075
MaterialBinding wire, per kg0.4 kg5%₦1,900₦798
Material1"x12"x12' plank (formwork)0.55 length10%₦6,500₦3,933
Material2"x3"x12' hardwood0.9 length10%₦3,500₦3,465
MaterialWire nails, assorted, per kg0.5 kg10%₦2,600₦1,430
Plant (days)Concrete mixer, 1-bag (petrol)0.03 day-₦43,546₦1,306
Plant (days)Poker vibrator (petrol)0.03 day-₦19,728₦592
Labour (hours)Mason / bricklayer0.5 h-₦2,456₦1,228
Labour (hours)Iron bender / steel fixer0.72 h-₦2,456₦1,768
Labour (hours)Carpenter (formwork & roof)2.4 h-₦2,784₦6,681
Labour (hours)Unskilled labourer8.4 h-₦1,146₦9,628
Materials₦80,967
Labour₦19,306
Plant₦1,898
Net unit rate per m₦102,171

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per mTender rate incl. OH&P and VAT
Abuja (FCT)₦102,171₦136,372
Lagos₦108,668₦145,045
Port Harcourt₦107,835₦143,932
Ibadan₦94,166₦125,688
Osogbo (Osun)₦94,049₦125,531
Kano₦91,582₦122,239
Kaduna₦92,971₦124,092
Enugu₦96,652₦129,007
Benin City₦97,886₦130,653
Uyo₦101,761₦135,825
Jos₦93,818₦125,224
Riverine / creek site₦129,151₦172,384

Related roads & external rates

Frequently asked questions

How much does in-situ RC drain 600x600 internal, 150mm walls & base, incl. excavation, formwork & rebar cost per m in Nigeria?

About ₦102,171 per m net in Abuja as at 15 October 2026, or about ₦136,372 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦108,668 per m and the tender rate about ₦145,045 per m.

What does the rate include?

Materials (1"x12"x12' plank (formwork), 2"x3"x12' hardwood, Binding wire, Granite 3/4", High-yield rebar 12-16mm, OPC 42.5 cement) with waste allowances; labour (Carpenter (formwork & roof), Iron bender / steel fixer, Mason / bricklayer, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Concrete mixer, 1-bag (petrol), Poker vibrator (petrol)) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/r10-in-situ-rc-drain-600x600-internal-150mm-walls-and-base-i/, prices as at 15 October 2026.