BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Thermoplastic road marking, 100mm line: cost per m in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦711per m

Tender rate about ₦949 per m with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for thermoplastic road marking, 100mm line is ₦711 per m in Abuja: ₦662 materials, ₦11.46 labour and ₦38.18 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦949 per m.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialThermoplastic road-marking material, per kg0.35 kg5%₦1,800₦662
Plant (days)Road line-marking machine0.0004 day-₦95,455₦38.18
Labour (hours)Unskilled labourer0.01 h-₦1,146₦11.46
Materials₦662
Labour₦11.46
Plant₦38.18
Net unit rate per m₦711

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per mTender rate incl. OH&P and VAT
Abuja (FCT)₦711₦949
Lagos₦754₦1,006
Port Harcourt₦767₦1,023
Ibadan₦674₦899
Osogbo (Osun)₦681₦909
Kano₦660₦881
Kaduna₦667₦890
Enugu₦695₦927
Benin City₦702₦938
Uyo₦730₦975
Jos₦674₦900
Riverine / creek site₦926₦1,236

Related roads & external rates

Frequently asked questions

How much does thermoplastic road marking, 100mm line cost per m in Nigeria?

About ₦711 per m net in Abuja as at 15 October 2026, or about ₦949 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦754 per m and the tender rate about ₦1,006 per m.

What does the rate include?

Materials (Thermoplastic road-marking material) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Road line-marking machine) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/r12-thermoplastic-road-marking-100mm-line/, prices as at 15 October 2026.