BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Excavate trench for strip foundation by hand, n.e. 1.5m deep, normal soil: cost per m³ in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦4,585per m³

Tender rate about ₦6,120 per m³ with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for excavate trench for strip foundation by hand, n.e. 1.5m deep, normal soil is ₦4,585 per m³ in Abuja: ₦0 materials, ₦4,585 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦6,120 per m³.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
Labour (hours)Unskilled labourer4 h-₦1,146₦4,585
Materials₦0
Labour₦4,585
Plant₦0
Net unit rate per m³₦4,585

Scope note: Excl. rock, dewatering, disposal.

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m³Tender rate incl. OH&P and VAT
Abuja (FCT)₦4,585₦6,120
Lagos₦4,952₦6,609
Port Harcourt₦4,356₦5,814
Ibadan₦3,668₦4,896
Osogbo (Osun)₦3,439₦4,590
Kano₦3,439₦4,590
Kaduna₦3,576₦4,773
Enugu₦3,668₦4,896
Benin City₦3,760₦5,018
Uyo₦3,897₦5,202
Jos₦3,576₦4,773
Riverine / creek site₦5,044₦6,732

Related earthworks rates

Frequently asked questions

How much does excavate trench for strip foundation by hand, n.e. 1.5m deep, normal soil cost per m³ in Nigeria?

About ₦4,585 per m³ net in Abuja as at 15 October 2026, or about ₦6,120 per m³ as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦4,952 per m³ and the tender rate about ₦6,609 per m³.

What does the rate include?

Materials (no materials) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate. Scope note: Excl. rock, dewatering, disposal.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/a02-excavate-trench-for-strip-foundation-by-hand-n-e-1-5m-de/, prices as at 15 October 2026.