Excavate trench by backhoe, n.e. 1.5m deep, trim by hand: cost per m³ in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦5,277per m³

Tender rate about ₦7,043 per m³ with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for excavate trench by backhoe, n.e. 1.5m deep, trim by hand is ₦5,277 per m³ in Abuja: ₦0 materials, ₦344 labour and ₦4,933 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦7,043 per m³.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
Plant (days)Backhoe loader (JCB 3CX/3DX class)0.01 day-₦493,290₦4,933
Labour (hours)Unskilled labourer0.3 h-₦1,146₦344
Materials₦0
Labour₦344
Plant₦4,933
Net unit rate per m³₦5,277

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m³Tender rate incl. OH&P and VAT
Abuja (FCT)₦5,277₦7,043
Lagos₦5,551₦7,409
Port Harcourt₦5,654₦7,547
Ibadan₦4,961₦6,622
Osogbo (Osun)₦5,043₦6,731
Kano₦4,944₦6,599
Kaduna₦4,954₦6,613
Enugu₦5,109₦6,820
Benin City₦5,215₦6,961
Uyo₦5,373₦7,172
Jos₦5,053₦6,745
Riverine / creek site₦7,284₦9,723

Related earthworks rates

Frequently asked questions

How much does excavate trench by backhoe, n.e. 1.5m deep, trim by hand cost per m³ in Nigeria?

About ₦5,277 per m³ net in Abuja as at 15 October 2026, or about ₦7,043 per m³ as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦5,551 per m³ and the tender rate about ₦7,409 per m³.

What does the rate include?

Materials (no materials) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Backhoe loader (JCB 3CX/3DX class)) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/a09-excavate-trench-by-backhoe-n-e-1-5m-deep-trim-by-hand/, prices as at 15 October 2026.