Keep excavations free of water - 3" pump incl. attendance: cost per day in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦26,656per day

Tender rate about ₦35,580 per day with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for keep excavations free of water - 3" pump incl. attendance is ₦26,656 per day in Abuja: ₦0 materials, ₦2,292 labour and ₦24,364 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦35,580 per day.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
Plant (days)Dewatering pump 3" (petrol)1 day-₦24,364₦24,364
Labour (hours)Unskilled labourer2 h-₦1,146₦2,292
Materials₦0
Labour₦2,292
Plant₦24,364
Net unit rate per day₦26,656

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per dayTender rate incl. OH&P and VAT
Abuja (FCT)₦26,656₦35,580
Lagos₦28,058₦37,450
Port Harcourt₦28,491₦38,028
Ibadan₦24,980₦33,342
Osogbo (Osun)₦25,352₦33,839
Kano₦24,865₦33,189
Kaduna₦24,934₦33,281
Enugu₦25,711₦34,317
Benin City₦26,244₦35,029
Uyo₦27,044₦36,096
Jos₦25,421₦33,931
Riverine / creek site₦36,631₦48,894

Related earthworks rates

Frequently asked questions

How much does keep excavations free of water - 3" pump incl. attendance cost per day in Nigeria?

About ₦26,656 per day net in Abuja as at 15 October 2026, or about ₦35,580 per day as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦28,058 per day and the tender rate about ₦37,450 per day.

What does the rate include?

Materials (no materials) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Dewatering pump 3" (petrol)) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/a11-keep-excavations-free-of-water-3-pump-incl-attendance/, prices as at 15 October 2026.