BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Clear site by bulldozer incl. grubbing roots: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦119per m²

Tender rate about ₦159 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for clear site by bulldozer incl. grubbing roots is ₦119 per m² in Abuja: ₦0 materials, ₦11.46 labour and ₦108 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦159 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
Plant (days)Bulldozer D6 class0.000125 day-₦862,180₦108
Labour (hours)Unskilled labourer0.01 h-₦1,146₦11.46
Materials₦0
Labour₦11.46
Plant₦108
Net unit rate per m²₦119

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦119₦159
Lagos₦126₦168
Port Harcourt₦127₦170
Ibadan₦112₦149
Osogbo (Osun)₦113₦151
Kano₦111₦148
Kaduna₦111₦149
Enugu₦115₦153
Benin City₦117₦156
Uyo₦121₦161
Jos₦113₦151
Riverine / creek site₦163₦218

Related earthworks rates

Frequently asked questions

How much does clear site by bulldozer incl. grubbing roots cost per m² in Nigeria?

About ₦119 per m² net in Abuja as at 15 October 2026, or about ₦159 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦126 per m² and the tender rate about ₦168 per m².

What does the rate include?

Materials (no materials) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Bulldozer D6 class) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/a14-clear-site-by-bulldozer-incl-grubbing-roots/, prices as at 15 October 2026.