BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Backfill with selected excavated material, compacted in 150mm layers: cost per m³ in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦2,899per m³

Tender rate about ₦3,870 per m³ with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for backfill with selected excavated material, compacted in 150mm layers is ₦2,899 per m³ in Abuja: ₦0 materials, ₦2,292 labour and ₦607 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦3,870 per m³.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
Labour (hours)Unskilled labourer2 h-₦1,146₦2,292
Plant (days)Plate compactor (petrol)0.025 day-₦24,273₦607
Materials₦0
Labour₦2,292
Plant₦607
Net unit rate per m³₦2,899

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m³Tender rate incl. OH&P and VAT
Abuja (FCT)₦2,899₦3,870
Lagos₦3,113₦4,155
Port Harcourt₦2,833₦3,782
Ibadan₦2,410₦3,217
Osogbo (Osun)₦2,308₦3,081
Kano₦2,296₦3,064
Kaduna₦2,365₦3,156
Enugu₦2,429₦3,242
Benin City₦2,487₦3,319
Uyo₦2,574₦3,435
Jos₦2,377₦3,172
Riverine / creek site₦3,371₦4,500

Related earthworks rates

Frequently asked questions

How much does backfill with selected excavated material, compacted in 150mm layers cost per m³ in Nigeria?

About ₦2,899 per m³ net in Abuja as at 15 October 2026, or about ₦3,870 per m³ as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦3,113 per m³ and the tender rate about ₦4,155 per m³.

What does the rate include?

Materials (no materials) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Plate compactor (petrol)) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/a04-backfill-with-selected-excavated-material-compacted-in-1/, prices as at 15 October 2026.