Imported laterite filling, compacted in 150mm layers: cost per m³ in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦12,309per m³

Tender rate about ₦16,430 per m³ with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for imported laterite filling, compacted in 150mm layers is ₦12,309 per m³ in Abuja: ₦9,896 materials, ₦1,719 labour and ₦694 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦16,430 per m³.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialLaterite, per tonne2.1 tonne5%₦4,250₦9,371
MaterialWater, per m30.15 m³-₦3,500₦525
Labour (hours)Unskilled labourer1.5 h-₦1,146₦1,719
Plant (days)Plate compactor (petrol)0.02857 day-₦24,273₦694
Materials₦9,896
Labour₦1,719
Plant₦694
Net unit rate per m³₦12,309

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m³Tender rate incl. OH&P and VAT
Abuja (FCT)₦12,309₦16,430
Lagos₦13,075₦17,452
Port Harcourt₦13,070₦17,446
Ibadan₦11,436₦15,264
Osogbo (Osun)₦11,463₦15,300
Kano₦11,152₦14,885
Kaduna₦11,302₦15,086
Enugu₦11,753₦15,688
Benin City₦11,901₦15,884
Uyo₦12,369₦16,509
Jos₦11,415₦15,236
Riverine / creek site₦15,727₦20,992

Related earthworks rates

Frequently asked questions

How much does imported laterite filling, compacted in 150mm layers cost per m³ in Nigeria?

About ₦12,309 per m³ net in Abuja as at 15 October 2026, or about ₦16,430 per m³ as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦13,075 per m³ and the tender rate about ₦17,452 per m³.

What does the rate include?

Materials (Laterite, Water) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Plate compactor (petrol)) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.