Dredge & hydraulically place sand fill by 12" CSD (in-situ m3): cost per m³ in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦3,483per m³

Tender rate about ₦4,649 per m³ with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for dredge & hydraulically place sand fill by 12" CSD (in-situ m3) is ₦3,483 per m³ in Abuja: ₦0 materials, ₦11.46 labour and ₦3,471 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦4,649 per m³.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
Plant (days)Cutter-suction dredger 12"0.000667 day-₦5,204,550₦3,471
Labour (hours)Unskilled labourer0.01 h-₦1,146₦11.46
Materials₦0
Labour₦11.46
Plant₦3,471
Net unit rate per m³₦3,483

Scope note: LOW - replace with FESTAC dredging log actuals. Excl. discharge pipeline & mob.

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m³Tender rate incl. OH&P and VAT
Abuja (FCT)₦3,483₦4,649
Lagos₦3,657₦4,882
Port Harcourt₦3,760₦5,019
Ibadan₦3,307₦4,414
Osogbo (Osun)₦3,376₦4,506
Kano₦3,306₦4,413
Kaduna₦3,307₦4,414
Enugu₦3,411₦4,553
Benin City₦3,481₦4,646
Uyo₦3,585₦4,785
Jos₦3,376₦4,506
Riverine / creek site₦4,873₦6,504

Related marine & dredging rates

Frequently asked questions

How much does dredge & hydraulically place sand fill by 12" CSD (in-situ m3) cost per m³ in Nigeria?

About ₦3,483 per m³ net in Abuja as at 15 October 2026, or about ₦4,649 per m³ as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦3,657 per m³ and the tender rate about ₦4,882 per m³.

What does the rate include?

Materials (no materials) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Cutter-suction dredger 12") including fuel and operator. Overheads, profit and VAT are excluded from the net rate. Scope note: LOW - replace with FESTAC dredging log actuals. Excl. discharge pipeline & mob.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/k01-dredge-and-hydraulically-place-sand-fill-by-12-csd-in-si/, prices as at 15 October 2026.