Crane rail A120 on grouted pads with clips: cost per m in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦472,073per m

Tender rate about ₦630,097 per m with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for crane rail A120 on grouted pads with clips is ₦472,073 per m in Abuja: ₦460,847 materials, ₦3,734 labour and ₦7,492 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦630,097 per m.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialCrane rail A120, per m1.02 m2%₦429,226₦446,567
MaterialNon-shrink cementitious grout, 25kg0.4 bag5%₦28,000₦11,760
MaterialBolt & nut M16x100 grade 8.8 with washers3 unit5%₦800₦2,520
Plant (days)Mobile crane 25t0.01 day-₦749,240₦7,492
Labour (hours)Welder / fabricator0.6 h-₦2,948₦1,768
Labour (hours)Rigger / banksman0.4 h-₦2,620₦1,048
Labour (hours)Unskilled labourer0.8 h-₦1,146₦917
Materials₦460,847
Labour₦3,734
Plant₦7,492
Net unit rate per m₦472,073

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per mTender rate incl. OH&P and VAT
Abuja (FCT)₦472,073₦630,097
Lagos₦500,397₦667,903
Port Harcourt₦509,353₦679,857
Ibadan₦447,909₦597,845
Osogbo (Osun)₦452,481₦603,947
Kano₦438,505₦585,294
Kaduna₦443,226₦591,594
Enugu₦461,959₦616,599
Benin City₦466,792₦623,049
Uyo₦485,563₦648,103
Jos₦447,984₦597,945
Riverine / creek site₦613,697₦819,130

Related marine & dredging rates

Frequently asked questions

How much does crane rail A120 on grouted pads with clips cost per m in Nigeria?

About ₦472,073 per m net in Abuja as at 15 October 2026, or about ₦630,097 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦500,397 per m and the tender rate about ₦667,903 per m.

What does the rate include?

Materials (Bolt & nut M16x100 grade 8.8 with washers, Crane rail A120, Non-shrink cementitious grout) with waste allowances; labour (Rigger / banksman, Unskilled labourer, Welder / fabricator) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Mobile crane 25t) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/k12-crane-rail-a120-on-grouted-pads-with-clips/, prices as at 15 October 2026.