BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Floating silt curtain deployed and maintained: cost per m in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦101,130per m

Tender rate about ₦134,983 per m with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for floating silt curtain deployed and maintained is ₦101,130 per m in Abuja: ₦98,759 materials, ₦1,228 labour and ₦1,142 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦134,983 per m.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialFloating silt curtain (turbidity barrier), per m1.05 m5%₦89,578₦98,759
Plant (days)Work boat with outboard0.005 day-₦228,450₦1,142
Labour (hours)Deckhand / marine crew0.5 h-₦2,456₦1,228
Materials₦98,759
Labour₦1,228
Plant₦1,142
Net unit rate per m₦101,130

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per mTender rate incl. OH&P and VAT
Abuja (FCT)₦101,130₦134,983
Lagos₦107,211₦143,099
Port Harcourt₦109,060₦145,568
Ibadan₦95,889₦127,988
Osogbo (Osun)₦96,838₦129,254
Kano₦93,852₦125,269
Kaduna₦94,877₦126,637
Enugu₦98,886₦131,988
Benin City₦99,921₦133,369
Uyo₦103,943₦138,737
Jos₦95,887₦127,985
Riverine / creek site₦131,337₦175,302

Related marine & dredging rates

Frequently asked questions

How much does floating silt curtain deployed and maintained cost per m in Nigeria?

About ₦101,130 per m net in Abuja as at 15 October 2026, or about ₦134,983 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦107,211 per m and the tender rate about ₦143,099 per m.

What does the rate include?

Materials (Floating silt curtain (turbidity barrier)) with waste allowances; labour (Deckhand / marine crew) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Work boat with outboard) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/k13-floating-silt-curtain-deployed-and-maintained/, prices as at 15 October 2026.