Geotextile under revetment laid incl. underwater placement: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦3,372per m²

Tender rate about ₦4,500 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for geotextile under revetment laid incl. underwater placement is ₦3,372 per m² in Abuja: ₦2,783 materials, ₦303 labour and ₦286 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦4,500 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialNon-woven needle-punched geotextile 400g/m2, per m21.15 m²10%₦2,200₦2,783
Plant (days)Work boat with outboard0.00125 day-₦228,450₦286
Labour (hours)Commercial diver0.01 h-₦24,562₦246
Labour (hours)Unskilled labourer0.05 h-₦1,146₦57.31
Materials₦2,783
Labour₦303
Plant₦286
Net unit rate per m²₦3,372

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦3,372₦4,500
Lagos₦3,577₦4,774
Port Harcourt₦3,602₦4,808
Ibadan₦3,157₦4,214
Osogbo (Osun)₦3,176₦4,239
Kano₦3,087₦4,120
Kaduna₦3,124₦4,169
Enugu₦3,250₦4,337
Benin City₦3,289₦4,390
Uyo₦3,418₦4,562
Jos₦3,157₦4,214
Riverine / creek site₦4,351₦5,807

Related marine & dredging rates

Frequently asked questions

How much does geotextile under revetment laid incl. underwater placement cost per m² in Nigeria?

About ₦3,372 per m² net in Abuja as at 15 October 2026, or about ₦4,500 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦3,577 per m² and the tender rate about ₦4,774 per m².

What does the rate include?

Materials (Non-woven needle-punched geotextile 400g/m2) with waste allowances; labour (Commercial diver, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Work boat with outboard) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/k08-geotextile-under-revetment-laid-incl-underwater-placemen/, prices as at 15 October 2026.