Armour rock 3-6t placed to revetment/breakwater profile: cost per tonne in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦46,643per tonne

Tender rate about ₦62,257 per tonne with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for armour rock 3-6t placed to revetment/breakwater profile is ₦46,643 per tonne in Abuja: ₦39,140 materials, ₦188 labour and ₦7,315 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦62,257 per tonne.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialArmour rock 3-6t, delivered to site, per tonne1 tonne3%₦38,000₦39,140
Plant (days)Hydraulic excavator 30t0.003333 day-₦1,141,840₦3,806
Plant (days)Mobile crane 80t0.001667 day-₦2,104,940₦3,509
Labour (hours)Rigger / banksman0.05 h-₦2,620₦131
Labour (hours)Unskilled labourer0.05 h-₦1,146₦57.31
Materials₦39,140
Labour₦188
Plant₦7,315
Net unit rate per tonne₦46,643

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per tonneTender rate incl. OH&P and VAT
Abuja (FCT)₦46,643₦62,257
Lagos₦49,372₦65,899
Port Harcourt₦50,350₦67,204
Ibadan₦44,283₦59,106
Osogbo (Osun)₦44,811₦59,811
Kano₦43,490₦58,049
Kaduna₦43,887₦58,579
Enugu₦45,676₦60,966
Benin City₦46,218₦61,689
Uyo₦48,008₦64,079
Jos₦44,425₦59,296
Riverine / creek site₦61,330₦81,860

Related marine & dredging rates

Frequently asked questions

How much does armour rock 3-6t placed to revetment/breakwater profile cost per tonne in Nigeria?

About ₦46,643 per tonne net in Abuja as at 15 October 2026, or about ₦62,257 per tonne as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦49,372 per tonne and the tender rate about ₦65,899 per tonne.

What does the rate include?

Materials (Armour rock 3-6t) with waste allowances; labour (Rigger / banksman, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Hydraulic excavator 30t, Mobile crane 80t) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/k05-armour-rock-3-6t-placed-to-revetment-breakwater-profile/, prices as at 15 October 2026.