BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Hydraulic sand fill by trailing suction hopper dredger (rainbowing/pump-ashore), placed: cost per m³ in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦2,907per m³

Tender rate about ₦3,881 per m³ with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for hydraulic sand fill by trailing suction hopper dredger (rainbowing/pump-ashore), placed is ₦2,907 per m³ in Abuja: ₦400 materials, ₦2.29 labour and ₦2,505 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦3,881 per m³.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialDredged sand licence/royalty & environmental levy, per m31 m³-₦400₦400
Plant (days)Trailing suction hopper dredger 5,000m33.3e-05 day-₦75,913,950₦2,505
Labour (hours)Unskilled labourer0.002 h-₦1,146₦2.29
Materials₦400
Labour₦2.29
Plant₦2,505
Net unit rate per m³₦2,907

Scope note: Large reclamations only; mobilisation of the dredger is a major separate cost.

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m³Tender rate incl. OH&P and VAT
Abuja (FCT)₦2,907₦3,881
Lagos₦3,057₦4,080
Port Harcourt₦3,140₦4,191
Ibadan₦2,762₦3,686
Osogbo (Osun)₦2,816₦3,758
Kano₦2,754₦3,675
Kaduna₦2,758₦3,681
Enugu₦2,849₦3,803
Benin City₦2,903₦3,875
Uyo₦2,994₦3,997
Jos₦2,812₦3,753
Riverine / creek site₦4,030₦5,379

Related marine & dredging rates

Frequently asked questions

How much does hydraulic sand fill by trailing suction hopper dredger (rainbowing/pump-ashore), placed cost per m³ in Nigeria?

About ₦2,907 per m³ net in Abuja as at 15 October 2026, or about ₦3,881 per m³ as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦3,057 per m³ and the tender rate about ₦4,080 per m³.

What does the rate include?

Materials (Dredged sand licence/royalty & environmental levy) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Trailing suction hopper dredger 5,000m3) including fuel and operator. Overheads, profit and VAT are excluded from the net rate. Scope note: Large reclamations only; mobilisation of the dredger is a major separate cost.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/k03-hydraulic-sand-fill-by-trailing-suction-hopper-dredger-r/, prices as at 15 October 2026.