BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Underlayer rock 50-300kg placed: cost per tonne in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦29,363per tonne

Tender rate about ₦39,192 per tonne with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for underlayer rock 50-300kg placed is ₦29,363 per tonne in Abuja: ₦26,780 materials, ₦45.85 labour and ₦2,537 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦39,192 per tonne.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialUnderlayer/filter rock 50-300kg, delivered, per tonne1 tonne3%₦26,000₦26,780
Plant (days)Hydraulic excavator 30t0.002222 day-₦1,141,840₦2,537
Labour (hours)Unskilled labourer0.04 h-₦1,146₦45.85
Materials₦26,780
Labour₦45.85
Plant₦2,537
Net unit rate per tonne₦29,363

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per tonneTender rate incl. OH&P and VAT
Abuja (FCT)₦29,363₦39,192
Lagos₦31,100₦41,511
Port Harcourt₦31,706₦42,320
Ibadan₦27,888₦37,223
Osogbo (Osun)₦28,204₦37,646
Kano₦27,350₦36,505
Kaduna₦27,619₦36,865
Enugu₦28,768₦38,397
Benin City₦29,087₦38,824
Uyo₦30,236₦40,357
Jos₦27,938₦37,290
Riverine / creek site₦38,416₦51,276

Related marine & dredging rates

Frequently asked questions

How much does underlayer rock 50-300kg placed cost per tonne in Nigeria?

About ₦29,363 per tonne net in Abuja as at 15 October 2026, or about ₦39,192 per tonne as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦31,100 per tonne and the tender rate about ₦41,511 per tonne.

What does the rate include?

Materials (Underlayer/filter rock 50-300kg) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Hydraulic excavator 30t) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/k07-underlayer-rock-50-300kg-placed/, prices as at 15 October 2026.