BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Cold mill existing asphalt 50mm and remove: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦1,992per m²

Tender rate about ₦2,658 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for cold mill existing asphalt 50mm and remove is ₦1,992 per m² in Abuja: ₦0 materials, ₦11.46 labour and ₦1,980 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦2,658 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
Plant (days)Cold milling machine0.000286 day-₦3,149,850₦901
Plant (days)Tipper truck 20t0.0025 day-₦423,040₦1,058
Plant (days)Mechanical road broom0.000125 day-₦174,460₦21.81
Labour (hours)Unskilled labourer0.01 h-₦1,146₦11.46
Materials₦0
Labour₦11.46
Plant₦1,980
Net unit rate per m²₦1,992

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦1,992₦2,658
Lagos₦2,092₦2,792
Port Harcourt₦2,150₦2,869
Ibadan₦1,890₦2,523
Osogbo (Osun)₦1,929₦2,575
Kano₦1,890₦2,522
Kaduna₦1,890₦2,523
Enugu₦1,950₦2,603
Benin City₦1,990₦2,656
Uyo₦2,049₦2,735
Jos₦1,930₦2,576
Riverine / creek site₦2,785₦3,717

Related roads & external rates

Frequently asked questions

How much does cold mill existing asphalt 50mm and remove cost per m² in Nigeria?

About ₦1,992 per m² net in Abuja as at 15 October 2026, or about ₦2,658 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦2,092 per m² and the tender rate about ₦2,792 per m².

What does the rate include?

Materials (no materials) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Cold milling machine, Mechanical road broom, Tipper truck 20t) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/r27-cold-mill-existing-asphalt-50mm-and-remove/, prices as at 15 October 2026.