BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Rubber speed hump installed: cost per m in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦40,053per m

Tender rate about ₦53,461 per m with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for rubber speed hump installed is ₦40,053 per m in Abuja: ₦39,480 materials, ₦573 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦53,461 per m.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialRubber speed hump module, per m1 m2%₦35,000₦35,700
MaterialExpansion anchor bolt M124 unit5%₦900₦3,780
Labour (hours)Unskilled labourer0.5 h-₦1,146₦573
Materials₦39,480
Labour₦573
Plant₦0
Net unit rate per m₦40,053

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per mTender rate incl. OH&P and VAT
Abuja (FCT)₦40,053₦53,461
Lagos₦42,468₦56,684
Port Harcourt₦43,183₦57,638
Ibadan₦37,964₦50,673
Osogbo (Osun)₦38,331₦51,162
Kano₦37,146₦49,581
Kaduna₦37,558₦50,131
Enugu₦39,149₦52,254
Benin City₦39,555₦52,796
Uyo₦41,152₦54,927
Jos₦37,953₦50,658
Riverine / creek site₦51,954₦69,346

Related roads & external rates

Frequently asked questions

How much does rubber speed hump installed cost per m in Nigeria?

About ₦40,053 per m net in Abuja as at 15 October 2026, or about ₦53,461 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦42,468 per m and the tender rate about ₦56,684 per m.

What does the rate include?

Materials (Expansion anchor bolt M12, Rubber speed hump module) with waste allowances; labour (Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/r28-rubber-speed-hump-installed/, prices as at 15 October 2026.