BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

HDPE PE100 SDR17 pipe 110mm laid and butt-fused in trench on sand bed: cost per m in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦10,487per m

Tender rate about ₦13,998 per m with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for hDPE PE100 SDR17 pipe 110mm laid and butt-fused in trench on sand bed is ₦10,487 per m in Abuja: ₦9,466 materials, ₦678 labour and ₦343 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦13,998 per m.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialHDPE PE100 SDR17 (PN10) pipe 110mm (2.02 kg/m), per m1.02 m3%₦8,486₦8,915
MaterialFilling sand, per tonne0.15 tonne5%₦3,500₦551
Plant (days)Generator 20kVA (diesel)0.0025 day-₦137,280₦343
Labour (hours)Plumber0.12 h-₦2,784₦334
Labour (hours)Unskilled labourer0.3 h-₦1,146₦344
Materials₦9,466
Labour₦678
Plant₦343
Net unit rate per m₦10,487

Scope note: Trench excavation excluded.

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per mTender rate incl. OH&P and VAT
Abuja (FCT)₦10,487₦13,998
Lagos₦11,127₦14,851
Port Harcourt₦11,238₦15,000
Ibadan₦9,861₦13,162
Osogbo (Osun)₦9,929₦13,252
Kano₦9,638₦12,864
Kaduna₦9,753₦13,018
Enugu₦10,155₦13,555
Benin City₦10,271₦13,709
Uyo₦10,680₦14,255
Jos₦9,855₦13,153
Riverine / creek site₦13,532₦18,062

Related water & sewerage rates

Frequently asked questions

How much does hDPE PE100 SDR17 pipe 110mm laid and butt-fused in trench on sand bed cost per m in Nigeria?

About ₦10,487 per m net in Abuja as at 15 October 2026, or about ₦13,998 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦11,127 per m and the tender rate about ₦14,851 per m.

What does the rate include?

Materials (Filling sand, HDPE PE100 SDR17 (PN10) pipe 110mm (2.02 kg/m)) with waste allowances; labour (Plumber, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Generator 20kVA (diesel)) including fuel and operator. Overheads, profit and VAT are excluded from the net rate. Scope note: Trench excavation excluded.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/v01-hdpe-pe100-sdr17-pipe-110mm-laid-and-butt-fused-in-trenc/, prices as at 15 October 2026.