uPVC sewer pipe 200mm laid on granular bed: cost per m in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦16,957per m

Tender rate about ₦22,634 per m with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for uPVC sewer pipe 200mm laid on granular bed is ₦16,957 per m in Abuja: ₦15,811 materials, ₦1,146 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦22,634 per m.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialuPVC structured-wall sewer pipe 200mm, per m1.02 m3%₦14,000₦14,708
MaterialFilling sand, per tonne0.3 tonne5%₦3,500₦1,102
Labour (hours)Pipe layer (drainage)0.25 h-₦2,292₦573
Labour (hours)Unskilled labourer0.5 h-₦1,146₦573
Materials₦15,811
Labour₦1,146
Plant₦0
Net unit rate per m₦16,957

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per mTender rate incl. OH&P and VAT
Abuja (FCT)₦16,957₦22,634
Lagos₦17,998₦24,022
Port Harcourt₦18,165₦24,245
Ibadan₦15,937₦21,272
Osogbo (Osun)₦16,038₦21,407
Kano₦15,564₦20,774
Kaduna₦15,756₦21,031
Enugu₦16,412₦21,905
Benin City₦16,593₦22,147
Uyo₦17,260₦23,037
Jos₦15,914₦21,242
Riverine / creek site₦21,815₦29,118

Related water & sewerage rates

Frequently asked questions

How much does uPVC sewer pipe 200mm laid on granular bed cost per m in Nigeria?

About ₦16,957 per m net in Abuja as at 15 October 2026, or about ₦22,634 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦17,998 per m and the tender rate about ₦24,022 per m.

What does the rate include?

Materials (Filling sand, uPVC structured-wall sewer pipe 200mm) with waste allowances; labour (Pipe layer (drainage), Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.