Bulk water meter DN100 with 2 valves in chamber: cost per unit in Nigeria
Net unit rate in Abuja, excluding overheads, profit and VAT
₦2,817,498per unit
Tender rate about ₦3,760,646 per unit with overheads, contingency, profit and VAT.
Price a BoQ with this rateAs at 15 October 2026, the net unit rate for bulk water meter DN100 with 2 valves in chamber is ₦2,817,498 per unit in Abuja: ₦2,771,484 materials, ₦46,014 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦3,760,646 per unit.
Rate build-up (Abuja, Oct 2026)
| Resource type | Resource | Quantity per unit | Waste | Rate | Cost |
|---|---|---|---|---|---|
| Material | Bulk water meter DN100 (Woltman) | 1 unit | - | ₦1,679,580 | ₦1,679,580 |
| Material | Resilient-seat gate valve DN100 PN16 (DI) | 2 unit | - | ₦485,212 | ₦970,424 |
| Material | 6" (150mm) hollow sandcrete block | 40 unit | 5% | ₦700 | ₦29,400 |
| Material | OPC 42.5 cement, 50kg bag - adopted market average | 3 bag | 3% | ₦12,000 | ₦37,080 |
| Material | Cast-iron manhole cover & frame, medium duty | 1 unit | - | ₦55,000 | ₦55,000 |
| Labour (hours) | Plumber | 8 h | - | ₦2,784 | ₦22,270 |
| Labour (hours) | Mason / bricklayer | 5 h | - | ₦2,456 | ₦12,281 |
| Labour (hours) | Unskilled labourer | 10 h | - | ₦1,146 | ₦11,462 |
| Materials | ₦2,771,484 | ||||
| Labour | ₦46,014 | ||||
| Plant | ₦0 | ||||
| Net unit rate per unit | ₦2,817,498 |
Rate by location
Materials, labour and plant are adjusted separately with Buildocrat's location factors.
| Location | Net rate per unit | Tender rate incl. OH&P and VAT |
|---|---|---|
| Abuja (FCT) | ₦2,817,498 | ₦3,760,646 |
| Lagos | ₦2,987,468 | ₦3,987,513 |
| Port Harcourt | ₦3,036,916 | ₦4,053,514 |
| Ibadan | ₦2,669,721 | ₦3,563,401 |
| Osogbo (Osun) | ₦2,695,135 | ₦3,597,323 |
| Kano | ₦2,611,990 | ₦3,486,346 |
| Kaduna | ₦2,641,086 | ₦3,525,181 |
| Enugu | ₦2,752,865 | ₦3,674,378 |
| Benin City | ₦2,781,500 | ₦3,712,599 |
| Uyo | ₦2,893,740 | ₦3,862,411 |
| Jos | ₦2,668,801 | ₦3,562,173 |
| Riverine / creek site | ₦3,653,544 | ₦4,876,557 |
Related water & sewerage rates
- V01 HDPE PE100 SDR17 pipe 110mm laid and butt-fused in trench on sand bed₦10,487 per m
- V02 HDPE PE100 SDR17 pipe 160mm laid and butt-fused in trench on sand bed₦20,958 per m
- V03 HDPE PE100 SDR17 pipe 250mm laid and butt-fused in trench on sand bed₦50,583 per m
- V04 HDPE PE100 SDR17 pipe 400mm laid and butt-fused in trench on sand bed₦124,777 per m
- V05 Ductile iron pipe DN150 laid in trench on sand bed₦55,966 per m
- V06 Ductile iron pipe DN300 laid in trench on sand bed₦124,862 per m
- V07 uPVC sewer pipe 200mm laid on granular bed₦16,957 per m
- V08 DI gate valve DN150 installed in block chamber with cover₦842,811 per unit
- V09 Pillar fire hydrant with isolating valve installed₦1,734,182 per unit
- V11 Domestic water connection 15mm with meter and stopcock₦71,610 per unit
- V12 Precast manhole 1200mm dia, 2m deep, with D400 cover₦854,353 per unit
- V13 Two-chamber septic tank (10m3) in solid blockwork with RC cover, and soakaway₦2,356,034 per unit
- V14 GRP sectional water tank on steel base frame, installed₦382,232 per m³
- V15 Package sewage treatment plant 50m3/day installed on concrete base₦92,587,570 per unit
- V16 Submersible pump 5.5HP installed in borehole with riser and cable₦1,515,016 per unit
- V17 Rapid gravity filter media (graded sand) placed₦61,093 per m³
- V18 Butterfly valve DN300 installed₦1,328,876 per unit
Frequently asked questions
How much does bulk water meter DN100 with 2 valves in chamber cost per unit in Nigeria?
About ₦2,817,498 per unit net in Abuja as at 15 October 2026, or about ₦3,760,646 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).
What is the rate in Lagos?
Applying Buildocrat's Lagos location factors, the net rate is about ₦2,987,468 per unit and the tender rate about ₦3,987,513 per unit.
What does the rate include?
Materials (6" (150mm) hollow sandcrete block, Bulk water meter DN100 (Woltman), Cast-iron manhole cover & frame, OPC 42.5 cement, Resilient-seat gate valve DN100 PN16 (DI)) with waste allowances; labour (Mason / bricklayer, Plumber, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.
How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/v10-bulk-water-meter-dn100-with-2-valves-in-chamber/, prices as at 15 October 2026.