Pillar fire hydrant with isolating valve installed: cost per unit in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦1,734,182per unit

Tender rate about ₦2,314,694 per unit with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for pillar fire hydrant with isolating valve installed is ₦1,734,182 per unit in Abuja: ₦1,710,602 materials, ₦23,580 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦2,314,694 per unit.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialPillar fire hydrant DN1001 unit-₦1,213,030₦1,213,030
MaterialResilient-seat gate valve DN100 PN16 (DI)1 unit-₦485,212₦485,212
MaterialOPC 42.5 cement, 50kg bag - adopted market average1 bag3%₦12,000₦12,360
Labour (hours)Plumber6 h-₦2,784₦16,702
Labour (hours)Unskilled labourer6 h-₦1,146₦6,878
Materials₦1,710,602
Labour₦23,580
Plant₦0
Net unit rate per unit₦1,734,182

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per unitTender rate incl. OH&P and VAT
Abuja (FCT)₦1,734,182₦2,314,694
Lagos₦1,838,705₦2,454,205
Port Harcourt₦1,869,851₦2,495,778
Ibadan₦1,643,936₦2,194,238
Osogbo (Osun)₦1,659,863₦2,215,497
Kano₦1,608,545₦2,147,000
Kaduna₦1,626,358₦2,170,777
Enugu₦1,695,254₦2,262,735
Benin City₦1,712,832₦2,286,197
Uyo₦1,781,963₦2,378,470
Jos₦1,643,464₦2,193,609
Riverine / creek site₦2,249,721₦3,002,808

Related water & sewerage rates

Frequently asked questions

How much does pillar fire hydrant with isolating valve installed cost per unit in Nigeria?

About ₦1,734,182 per unit net in Abuja as at 15 October 2026, or about ₦2,314,694 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦1,838,705 per unit and the tender rate about ₦2,454,205 per unit.

What does the rate include?

Materials (OPC 42.5 cement, Pillar fire hydrant DN100, Resilient-seat gate valve DN100 PN16 (DI)) with waste allowances; labour (Plumber, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/v09-pillar-fire-hydrant-with-isolating-valve-installed/, prices as at 15 October 2026.