Package sewage treatment plant 50m3/day installed on concrete base: cost per unit in Nigeria
Net unit rate in Abuja, excluding overheads, profit and VAT
₦92,587,570per unit
Tender rate about ₦123,580,970 per unit with overheads, contingency, profit and VAT.
Price a BoQ with this rateAs at 15 October 2026, the net unit rate for package sewage treatment plant 50m3/day installed on concrete base is ₦92,587,570 per unit in Abuja: ₦91,585,500 materials, ₦252,830 labour and ₦749,240 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦123,580,970 per unit.
Rate build-up (Abuja, Oct 2026)
| Resource type | Resource | Quantity per unit | Waste | Rate | Cost |
|---|---|---|---|---|---|
| Material | Package sewage treatment plant 50m3/day | 1 unit | - | ₦89,577,600 | ₦89,577,600 |
| Material | Ready-mix C25/30, delivered Abuja (ex-pump) | 8 m³ | 2% | ₦165,000 | ₦1,346,400 |
| Material | High-yield rebar 12-16mm, per tonne | 0.6 tonne | 5% | ₦1,050,000 | ₦661,500 |
| Plant (days) | Mobile crane 25t | 1 day | - | ₦749,240 | ₦749,240 |
| Labour (hours) | Plumber | 40 h | - | ₦2,784 | ₦111,350 |
| Labour (hours) | Electrician | 24 h | - | ₦3,029 | ₦72,705 |
| Labour (hours) | Unskilled labourer | 60 h | - | ₦1,146 | ₦68,775 |
| Materials | ₦91,585,500 | ||||
| Labour | ₦252,830 | ||||
| Plant | ₦749,240 | ||||
| Net unit rate per unit | ₦92,587,570 |
Rate by location
Materials, labour and plant are adjusted separately with Buildocrat's location factors.
| Location | Net rate per unit | Tender rate incl. OH&P and VAT |
|---|---|---|
| Abuja (FCT) | ₦92,587,570 | ₦123,580,970 |
| Lagos | ₦98,140,388 | ₦130,992,577 |
| Port Harcourt | ₦99,961,708 | ₦133,423,577 |
| Ibadan | ₦87,920,267 | ₦117,351,302 |
| Osogbo (Osun) | ₦88,838,465 | ₦118,576,864 |
| Kano | ₦86,075,916 | ₦114,889,559 |
| Kaduna | ₦86,999,355 | ₦116,122,118 |
| Enugu | ₦90,690,309 | ₦121,048,607 |
| Benin City | ₦91,626,206 | ₦122,297,792 |
| Uyo | ₦95,319,688 | ₦127,227,655 |
| Jos | ₦87,930,195 | ₦117,364,553 |
| Riverine / creek site | ₦120,388,199 | ₦160,687,772 |
Related water & sewerage rates
- V01 HDPE PE100 SDR17 pipe 110mm laid and butt-fused in trench on sand bed₦10,487 per m
- V02 HDPE PE100 SDR17 pipe 160mm laid and butt-fused in trench on sand bed₦20,958 per m
- V03 HDPE PE100 SDR17 pipe 250mm laid and butt-fused in trench on sand bed₦50,583 per m
- V04 HDPE PE100 SDR17 pipe 400mm laid and butt-fused in trench on sand bed₦124,777 per m
- V05 Ductile iron pipe DN150 laid in trench on sand bed₦55,966 per m
- V06 Ductile iron pipe DN300 laid in trench on sand bed₦124,862 per m
- V07 uPVC sewer pipe 200mm laid on granular bed₦16,957 per m
- V08 DI gate valve DN150 installed in block chamber with cover₦842,811 per unit
- V09 Pillar fire hydrant with isolating valve installed₦1,734,182 per unit
- V10 Bulk water meter DN100 with 2 valves in chamber₦2,817,498 per unit
- V11 Domestic water connection 15mm with meter and stopcock₦71,610 per unit
- V12 Precast manhole 1200mm dia, 2m deep, with D400 cover₦854,353 per unit
- V13 Two-chamber septic tank (10m3) in solid blockwork with RC cover, and soakaway₦2,356,034 per unit
- V14 GRP sectional water tank on steel base frame, installed₦382,232 per m³
- V16 Submersible pump 5.5HP installed in borehole with riser and cable₦1,515,016 per unit
- V17 Rapid gravity filter media (graded sand) placed₦61,093 per m³
- V18 Butterfly valve DN300 installed₦1,328,876 per unit
Frequently asked questions
How much does package sewage treatment plant 50m3/day installed on concrete base cost per unit in Nigeria?
About ₦92,587,570 per unit net in Abuja as at 15 October 2026, or about ₦123,580,970 per unit as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).
What is the rate in Lagos?
Applying Buildocrat's Lagos location factors, the net rate is about ₦98,140,388 per unit and the tender rate about ₦130,992,577 per unit.
What does the rate include?
Materials (High-yield rebar 12-16mm, Package sewage treatment plant 50m3/day, Ready-mix C25/30) with waste allowances; labour (Electrician, Plumber, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Mobile crane 25t) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.