Ductile iron pipe DN150 laid in trench on sand bed: cost per m in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦55,966per m

Tender rate about ₦74,700 per m with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for ductile iron pipe DN150 laid in trench on sand bed is ₦55,966 per m in Abuja: ₦52,905 materials, ₦1,244 labour and ₦1,816 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦74,700 per m.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialDuctile iron pipe DN150 K9 push-fit (25.5 kg/m), per m1.02 m2%₦49,968₦51,986
MaterialFilling sand, per tonne0.25 tonne5%₦3,500₦919
Plant (days)Hydraulic excavator 14t0.003333 day-₦545,000₦1,816
Labour (hours)Plumber0.2 h-₦2,784₦557
Labour (hours)Unskilled labourer0.6 h-₦1,146₦688
Materials₦52,905
Labour₦1,244
Plant₦1,816
Net unit rate per m₦55,966

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per mTender rate incl. OH&P and VAT
Abuja (FCT)₦55,966₦74,700
Lagos₦59,331₦79,191
Port Harcourt₦60,281₦80,460
Ibadan₦52,981₦70,716
Osogbo (Osun)₦53,484₦71,388
Kano₦51,861₦69,221
Kaduna₦52,427₦69,977
Enugu₦54,623₦72,907
Benin City₦55,213₦73,695
Uyo₦57,421₦76,642
Jos₦52,992₦70,731
Riverine / creek site₦72,688₦97,021

Related water & sewerage rates

Frequently asked questions

How much does ductile iron pipe DN150 laid in trench on sand bed cost per m in Nigeria?

About ₦55,966 per m net in Abuja as at 15 October 2026, or about ₦74,700 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦59,331 per m and the tender rate about ₦79,191 per m.

What does the rate include?

Materials (Ductile iron pipe DN150 K9 push-fit (25.5 kg/m), Filling sand) with waste allowances; labour (Plumber, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Hydraulic excavator 14t) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/v05-ductile-iron-pipe-dn150-laid-in-trench-on-sand-bed/, prices as at 15 October 2026.