BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

GRP sectional water tank on steel base frame, installed: cost per m³ in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦382,232per m³

Tender rate about ₦510,182 per m³ with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for gRP sectional water tank on steel base frame, installed is ₦382,232 per m³ in Abuja: ₦373,978 materials, ₦8,253 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦510,182 per m³.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialGRP sectional water tank, per m3 capacity1 m³-₦335,916₦335,916
MaterialStructural steel sections (UB/UC/PFC/angle), per tonne0.025 tonne5%₦1,450,000₦38,062
Labour (hours)Welder / fabricator0.8 h-₦2,948₦2,358
Labour (hours)Plumber1.5 h-₦2,784₦4,176
Labour (hours)Unskilled labourer1.5 h-₦1,146₦1,719
Materials₦373,978
Labour₦8,253
Plant₦0
Net unit rate per m³₦382,232

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m³Tender rate incl. OH&P and VAT
Abuja (FCT)₦382,232₦510,182
Lagos₦405,330₦541,014
Port Harcourt₦411,737₦549,565
Ibadan₦361,882₦483,021
Osogbo (Osun)₦365,209₦487,462
Kano₦353,990₦472,487
Kaduna₦357,977₦477,809
Enugu₦373,101₦497,996
Benin City₦377,006₦503,208
Uyo₦392,213₦523,505
Jos₦361,717₦482,801
Riverine / creek site₦495,250₦661,034

Related water & sewerage rates

Frequently asked questions

How much does gRP sectional water tank on steel base frame, installed cost per m³ in Nigeria?

About ₦382,232 per m³ net in Abuja as at 15 October 2026, or about ₦510,182 per m³ as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦405,330 per m³ and the tender rate about ₦541,014 per m³.

What does the rate include?

Materials (GRP sectional water tank, Structural steel sections (UB/UC/PFC/angle)) with waste allowances; labour (Plumber, Unskilled labourer, Welder / fabricator) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/v14-grp-sectional-water-tank-on-steel-base-frame-installed/, prices as at 15 October 2026.