Construction costs in Osogbo (Osun)

As at 15 October 2026, Buildocrat estimates a 50kg bag of cement at about ₦11,520 in Osogbo (Osun), a mason at about ₦11,250 a day, and 225mm blockwork at about ₦11,917 per m² net. Rates for Osogbo (Osun) apply location factors to the Abuja base: materials 0.96, labour 0.75, plant 0.97.

Key material prices in Osogbo (Osun)

MaterialUnitEstimated price
OPC 42.5 cement, 50kg bag - adopted market averagebag₦11,520
High-yield rebar 12-16mm, per tonnetonne₦1,008,000
9" (225mm) hollow sandcrete blockunit₦816
Sharp sand, 20t tipper loadload₦124,800
Granite 3/4", 30t loadload₦518,400
Aluminium longspan 0.55mm, Grade A (market)m²₦7,776
Floor tile 600x600 ceramic/porcelain, mid-rangem²₦8,160
Emulsion paint, standard, 20L20L pail₦48,000
2"x4"x12' hardwood (Gmelina/Akpontu)length₦4,608
Diesel (AGO), pump price, per litrelitre₦1,795
Polyethylene water tank 2,000Lunit₦249,600
Hybrid inverter 5kVA/48Vunit₦480,000
Ready-mix C25/30, delivered Abuja (ex-pump)m³₦158,400
2.5mm2 single-core Cu cable, 100m coil100m coil₦73,920
Aluminium casement window, 5mm glass & net - supply & fixm²₦91,200
API 5L X52 line pipe 12" (323.9x9.53mm, 73.9 kg/m), bare, per mm₦132,360
Sheet pile PU18 (128 kg/m2 of wall), per m2m²₦194,921
HDPE PE100 SDR17 (PN10) pipe 110mm (2.02 kg/m), per mm₦8,146
33kV 1-core 240mm2 Cu XLPE/SWA cable, per mm₦50,880
Dry powder extinguisher 9kgunit₦43,200
Wheelbarrow heavy dutyunit₦62,400
Armour rock 3-6t, delivered to site, per tonnetonne₦36,480
Excavator 20-22t (CAT 320D/320GC), foreign usedunit₦163,200,000
Bulldozer D6 class (CAT D6H/D6R), foreign usedunit₦192,000,000
Motor grader CAT 140G, Nigerian usedunit₦76,800,000
Tipper truck 6x4 371hp 30t (Sinotruk Howo), newunit₦96,000,000
Truck crane 50-55t (SANY/XCMG), foreign usedunit₦134,400,000
Diesel generator 100kVA soundproof (Mikano), newunit₦17,280,000
Concrete batching plant 50 m3/h, newunit₦163,200,000
Block moulding line FT4-5 / mobile type (~3,000 blocks/day)unit₦4,992,000
Crushing plant 200 t/h (jaw + cone + screens), Nigerian usedunit₦168,000,000
Suction dredger 10-12", Nigerian usedunit₦43,200,000
Rotary bored-pile rig 150-200kNm (SANY SR150/Bauer BG), foreign usedunit₦432,000,000
Total station 2" (Leica/Sokkia/Topcon), newunit₦16,123,968

Labour rates in Osogbo (Osun)

TradeDaily wageAll-in day
Mason / bricklayer₦11,250₦14,738
Unskilled labourer₦5,250₦6,878
Carpenter (formwork & roof)₦12,750₦16,702
Iron bender / steel fixer₦11,250₦14,738
Electrician₦13,875₦18,176
Plumber₦12,750₦16,702
Tiler₦11,250₦14,738
Painter₦9,375₦12,281
Plasterer / screeder₦10,125₦13,264
Welder / fabricator₦13,500₦17,685

Common BoQ rates in Osogbo (Osun)

ItemUnitNet rateTender rate
225mm hollow sandcrete blockwork in cement-sand mortar 1:6m²₦11,917₦15,906
150mm hollow sandcrete blockwork in cement-sand mortar 1:6m²₦9,555₦12,753
Reinforced concrete 1:2:4 in foundations / bases / ground beamsm³₦119,967₦160,126
Reinforced concrete 1:2:4 in suspended slabs, beams & columnsm³₦126,271₦168,540
High-yield reinforcement 12-16mm, cut, bent & fixedtonne₦1,142,789₦1,525,334
Formwork (marine board) to soffit of suspended slab incl. propping n.e. 3.5mm²₦9,773₦13,045
Formwork (marine board) to columns and beamsm²₦9,387₦12,529
15mm internal plaster, cement-sand 1:6, to blockworkm²₦2,699₦3,603
20mm external render, cement-sand 1:4m²₦4,051₦5,408
40mm cement-sand 1:3 floor screedm²₦5,776₦7,710
600x600 ceramic floor tiles (mid-range) on adhesive, groutedm²₦12,899₦17,217
Skim coat + 3 coats emulsion to internal plastered wallsm²₦2,117₦2,826
2 coats weathershield paint to external renderm²₦1,418₦1,893
Timber roof: 2x4 trusses/rafters, 2x3 purlins, 2x6 wall plate, treated (slope area)m²₦7,928₦10,582
0.55mm longspan aluminium (Grade A) on timber purlins incl. laps, ridges & fixingsm²₦10,184₦13,593
Stone-coated steel tiles on 2x2 battens incl. fixingsm²₦15,386₦20,537
Aluminium casement window, 5mm glass & net, s&f incl. making goodm²₦91,990₦122,783
Lighting point: 1.5mm2 in 20mm conduit (avg 8m), switch share, LED downlightpoint₦26,953₦35,975
13A socket point: 2.5mm2 in 20mm conduit (avg 10m), twin socketpoint₦36,702₦48,987
Asphalt wearing course 50mm, laid & compactedm²₦19,660₦26,241
60mm interlocking paving on 50mm sand bed, compactedm²₦10,423₦13,912
225mm block fence wall 2.4m high incl. foundation, piers, plaster both sides & razor wirem₦76,110₦101,588

Location factors are starting points based on market evidence and judgement; confirm with local quotes. How the factors work.

Frequently asked questions

How much is cement in Osogbo (Osun)?

About ₦11,520 per 50kg bag (Buildocrat estimate, 15 October 2026).

How much is a mason paid per day in Osogbo (Osun)?

About ₦11,250 a day, or ₦14,738 all-in.

How much does blockwork cost per square metre in Osogbo (Osun)?

225mm hollow sandcrete blockwork is about ₦11,917 per m² net, or ₦15,906 including overheads, profit and VAT.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/locations/osogbo-osun/, prices as at 15 October 2026.