Formwork (marine board) to columns and beams: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦11,003per m²

Tender rate about ₦14,686 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for formwork (marine board) to columns and beams is ₦11,003 per m² in Abuja: ₦5,403 materials, ₦5,600 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦14,686 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialMarine board 18mm, 4'x8' film-faced0.09 sheet5%₦32,000₦3,024
Material2"x3"x12' hardwood0.45 length10%₦3,500₦1,733
MaterialWire nails, assorted, per kg0.18 kg10%₦2,600₦515
MaterialFormwork release oil, per litre0.05 litre5%₦2,500₦131
Labour (hours)Carpenter (formwork & roof)1.6 h-₦2,784₦4,454
Labour (hours)Unskilled labourer1 h-₦1,146₦1,146
Materials₦5,403
Labour₦5,600
Plant₦0
Net unit rate per m²₦11,003

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦11,003₦14,686
Lagos₦11,775₦15,717
Port Harcourt₦11,155₦14,889
Ibadan₦9,613₦12,830
Osogbo (Osun)₦9,387₦12,529
Kano₦9,225₦12,312
Kaduna₦9,447₦12,609
Enugu₦9,775₦13,047
Benin City₦9,941₦13,268
Uyo₦10,325₦13,781
Jos₦9,501₦12,681
Riverine / creek site₦13,184₦17,597

Related concrete rates

Frequently asked questions

How much does formwork (marine board) to columns and beams cost per m² in Nigeria?

About ₦11,003 per m² net in Abuja as at 15 October 2026, or about ₦14,686 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦11,775 per m² and the tender rate about ₦15,717 per m².

What does the rate include?

Materials (2"x3"x12' hardwood, Formwork release oil, Marine board 18mm, Wire nails) with waste allowances; labour (Carpenter (formwork & roof), Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.