BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Formwork (plank) to sides of foundations & ground beams: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦7,457per m²

Tender rate about ₦9,954 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for formwork (plank) to sides of foundations & ground beams is ₦7,457 per m² in Abuja: ₦3,757 materials, ₦3,701 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦9,954 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
Material1"x12"x12' plank (formwork)0.23 length10%₦6,500₦1,645
Material2"x3"x12' hardwood0.4 length10%₦3,500₦1,540
MaterialWire nails, assorted, per kg0.2 kg10%₦2,600₦572
Labour (hours)Carpenter (formwork & roof)1 h-₦2,784₦2,784
Labour (hours)Unskilled labourer0.8 h-₦1,146₦917
Materials₦3,757
Labour₦3,701
Plant₦0
Net unit rate per m²₦7,457

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦7,457₦9,954
Lagos₦7,979₦10,650
Port Harcourt₦7,573₦10,108
Ibadan₦6,529₦8,715
Osogbo (Osun)₦6,382₦8,518
Kano₦6,269₦8,368
Kaduna₦6,418₦8,566
Enugu₦6,642₦8,865
Benin City₦6,754₦9,014
Uyo₦7,015₦9,363
Jos₦6,455₦8,616
Riverine / creek site₦8,954₦11,952

Related concrete rates

Frequently asked questions

How much does formwork (plank) to sides of foundations & ground beams cost per m² in Nigeria?

About ₦7,457 per m² net in Abuja as at 15 October 2026, or about ₦9,954 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦7,979 per m² and the tender rate about ₦10,650 per m².

What does the rate include?

Materials (1"x12"x12' plank (formwork), 2"x3"x12' hardwood, Wire nails) with waste allowances; labour (Carpenter (formwork & roof), Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/b07-formwork-plank-to-sides-of-foundations-and-ground-beams/, prices as at 15 October 2026.