Formwork to staircase soffits, strings & risers: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦16,935per m²

Tender rate about ₦22,604 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for formwork to staircase soffits, strings & risers is ₦16,935 per m² in Abuja: ₦8,256 materials, ₦8,679 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦22,604 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialMarine board 18mm, 4'x8' film-faced0.12 sheet5%₦32,000₦4,032
Material2"x4"x12' hardwood (Gmelina/Akpontu)0.4 length10%₦4,800₦2,112
Material2"x3"x12' hardwood0.4 length10%₦3,500₦1,540
MaterialWire nails, assorted, per kg0.2 kg10%₦2,600₦572
Labour (hours)Carpenter (formwork & roof)2.5 h-₦2,784₦6,959
Labour (hours)Unskilled labourer1.5 h-₦1,146₦1,719
Materials₦8,256
Labour₦8,679
Plant₦0
Net unit rate per m²₦16,935

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦16,935₦22,604
Lagos₦18,124₦24,191
Port Harcourt₦17,161₦22,906
Ibadan₦14,786₦19,736
Osogbo (Osun)₦14,435₦19,267
Kano₦14,187₦18,936
Kaduna₦14,530₦19,394
Enugu₦15,034₦20,066
Benin City₦15,290₦20,408
Uyo₦15,881₦21,197
Jos₦14,613₦19,504
Riverine / creek site₦20,279₦27,068

Related concrete rates

Frequently asked questions

How much does formwork to staircase soffits, strings & risers cost per m² in Nigeria?

About ₦16,935 per m² net in Abuja as at 15 October 2026, or about ₦22,604 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦18,124 per m² and the tender rate about ₦24,191 per m².

What does the rate include?

Materials (2"x3"x12' hardwood, 2"x4"x12' hardwood (Gmelina/Akpontu), Marine board 18mm, Wire nails) with waste allowances; labour (Carpenter (formwork & roof), Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/b14-formwork-to-staircase-soffits-strings-and-risers/, prices as at 15 October 2026.