BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

BRC mesh A142 in ground slab incl. laps: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦5,113per m²

Tender rate about ₦6,825 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for bRC mesh A142 in ground slab incl. laps is ₦5,113 per m² in Abuja: ₦4,933 materials, ₦180 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦6,825 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialBRC mesh A142, per m21.15 m²10%₦3,800₦4,807
MaterialConcrete cover spacers, per 1000.04 pack5%₦3,000₦126
Labour (hours)Iron bender / steel fixer0.05 h-₦2,456₦123
Labour (hours)Unskilled labourer0.05 h-₦1,146₦57.31
Materials₦4,933
Labour₦180
Plant₦0
Net unit rate per m²₦5,113

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦5,113₦6,825
Lagos₦5,424₦7,239
Port Harcourt₦5,499₦7,339
Ibadan₦4,830₦6,447
Osogbo (Osun)₦4,871₦6,501
Kano₦4,723₦6,304
Kaduna₦4,778₦6,377
Enugu₦4,978₦6,645
Benin City₦5,031₦6,716
Uyo₦5,234₦6,986
Jos₦4,827₦6,443
Riverine / creek site₦6,611₦8,824

Related concrete rates

Frequently asked questions

How much does bRC mesh A142 in ground slab incl. laps cost per m² in Nigeria?

About ₦5,113 per m² net in Abuja as at 15 October 2026, or about ₦6,825 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦5,424 per m² and the tender rate about ₦7,239 per m².

What does the rate include?

Materials (BRC mesh A142, Concrete cover spacers) with waste allowances; labour (Iron bender / steel fixer, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/b10-brc-mesh-a142-in-ground-slab-incl-laps/, prices as at 15 October 2026.