Formwork (marine board) to walls: cost per m² in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦10,639per m²

Tender rate about ₦14,200 per m² with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for formwork (marine board) to walls is ₦10,639 per m² in Abuja: ₦5,595 materials, ₦5,044 labour and ₦0 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦14,200 per m².

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialMarine board 18mm, 4'x8' film-faced0.09 sheet5%₦32,000₦3,024
Material2"x3"x12' hardwood0.5 length10%₦3,500₦1,925
MaterialWire nails, assorted, per kg0.18 kg10%₦2,600₦515
MaterialFormwork release oil, per litre0.05 litre5%₦2,500₦131
Labour (hours)Carpenter (formwork & roof)1.4 h-₦2,784₦3,897
Labour (hours)Unskilled labourer1 h-₦1,146₦1,146
Materials₦5,595
Labour₦5,044
Plant₦0
Net unit rate per m²₦10,639

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m²Tender rate incl. OH&P and VAT
Abuja (FCT)₦10,639₦14,200
Lagos₦11,378₦15,186
Port Harcourt₦10,834₦14,461
Ibadan₦9,350₦12,480
Osogbo (Osun)₦9,154₦12,218
Kano₦8,986₦11,994
Kaduna₦9,193₦12,271
Enugu₦9,518₦12,704
Benin City₦9,675₦12,913
Uyo₦10,050₦13,414
Jos₦9,249₦12,345
Riverine / creek site₦12,821₦17,113

Related concrete rates

Frequently asked questions

How much does formwork (marine board) to walls cost per m² in Nigeria?

About ₦10,639 per m² net in Abuja as at 15 October 2026, or about ₦14,200 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦11,378 per m² and the tender rate about ₦15,186 per m².

What does the rate include?

Materials (2"x3"x12' hardwood, Formwork release oil, Marine board 18mm, Wire nails) with waste allowances; labour (Carpenter (formwork & roof), Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (no plant) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.