Formwork to slab using steel props (props hired): cost per m² in Nigeria
Net unit rate in Abuja, excluding overheads, profit and VAT
₦10,545per m²
Tender rate about ₦14,075 per m² with overheads, contingency, profit and VAT.
Price a BoQ with this rateAs at 15 October 2026, the net unit rate for formwork to slab using steel props (props hired) is ₦10,545 per m² in Abuja: ₦3,958 materials, ₦4,487 labour and ₦2,100 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦14,075 per m².
Rate build-up (Abuja, Oct 2026)
| Resource type | Resource | Quantity per unit | Waste | Rate | Cost |
|---|---|---|---|---|---|
| Material | Marine board 18mm, 4'x8' film-faced | 0.07 sheet | 5% | ₦32,000 | ₦2,352 |
| Material | 2"x4"x12' hardwood (Gmelina/Akpontu) | 0.25 length | 10% | ₦4,800 | ₦1,320 |
| Material | Wire nails, assorted, per kg | 0.1 kg | 10% | ₦2,600 | ₦286 |
| Plant (days) | Adjustable steel props, per 100 nr | 0.14 day | - | ₦15,000 | ₦2,100 |
| Labour (hours) | Carpenter (formwork & roof) | 1.2 h | - | ₦2,784 | ₦3,340 |
| Labour (hours) | Unskilled labourer | 1 h | - | ₦1,146 | ₦1,146 |
| Materials | ₦3,958 | ||||
| Labour | ₦4,487 | ||||
| Plant | ₦2,100 | ||||
| Net unit rate per m² | ₦10,545 |
Rate by location
Materials, labour and plant are adjusted separately with Buildocrat's location factors.
| Location | Net rate per m² | Tender rate incl. OH&P and VAT |
|---|---|---|
| Abuja (FCT) | ₦10,545 | ₦14,075 |
| Lagos | ₦11,246 | ₦15,011 |
| Port Harcourt | ₦10,805 | ₦14,422 |
| Ibadan | ₦9,344 | ₦12,473 |
| Osogbo (Osun) | ₦9,202 | ₦12,282 |
| Kano | ₦9,041 | ₦12,067 |
| Kaduna | ₦9,215 | ₦12,300 |
| Enugu | ₦9,526 | ₦12,715 |
| Benin City | ₦9,698 | ₦12,944 |
| Uyo | ₦10,053 | ₦13,419 |
| Jos | ₦9,297 | ₦12,409 |
| Riverine / creek site | ₦13,021 | ₦17,380 |
Related concrete rates
- B01 Plain concrete 1:3:6 in blinding (site-mixed)₦98,716 per m³
- B02 Reinforced concrete 1:2:4 in foundations / bases / ground beams₦127,723 per m³
- B03 Reinforced concrete 1:2:4 in suspended slabs, beams & columns₦135,819 per m³
- B04 Reinforced concrete 1:1.5:3 (~C25) in suspended slabs & beams₦155,521 per m³
- B05 Ready-mix C25/30 placed by pump in suspended slab₦181,224 per m³
- B15 Ready-mix C30/37 placed by pump in columns & walls₦198,104 per m³
- B18 Ready-mix C35/45 placed by boom pump in raft/transfer slab₦204,739 per m³
- B06 High-yield reinforcement 12-16mm, cut, bent & fixed₦1,208,315 per tonne
- B11 High-yield reinforcement 20-25mm, cut, bent & fixed₦1,202,012 per tonne
- B12 Reinforcement 8-10mm links/stirrups, cut, bent & fixed₦1,306,845 per tonne
- B10 BRC mesh A142 in ground slab incl. laps₦5,113 per m²
- B07 Formwork (plank) to sides of foundations & ground beams₦7,457 per m²
- B08 Formwork (marine board) to soffit of suspended slab incl. propping n.e. 3.5m₦11,395 per m²
- B09 Formwork (marine board) to columns and beams₦11,003 per m²
- B13 Formwork (marine board) to walls₦10,639 per m²
- B14 Formwork to staircase soffits, strings & risers₦16,935 per m²
- B16 Power-floated finish to concrete slab₦377 per m²
- B17 Precast lintel 150x225x1500, supply and bed in mortar₦19,688 per unit
Frequently asked questions
How much does formwork to slab using steel props (props hired) cost per m² in Nigeria?
About ₦10,545 per m² net in Abuja as at 15 October 2026, or about ₦14,075 per m² as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).
What is the rate in Lagos?
Applying Buildocrat's Lagos location factors, the net rate is about ₦11,246 per m² and the tender rate about ₦15,011 per m².
What does the rate include?
Materials (2"x4"x12' hardwood (Gmelina/Akpontu), Marine board 18mm, Wire nails) with waste allowances; labour (Carpenter (formwork & roof), Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Adjustable steel props, per 100 nr) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.
How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/b19-formwork-to-slab-using-steel-props-props-hired/, prices as at 15 October 2026.