BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Plain concrete 1:3:6 in blinding (site-mixed): cost per m³ in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦98,716per m³

Tender rate about ₦131,761 per m³ with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for plain concrete 1:3:6 in blinding (site-mixed) is ₦98,716 per m³ in Abuja: ₦86,480 materials, ₦9,334 labour and ₦2,903 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦131,761 per m³.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialOPC 42.5 cement, 50kg bag - adopted market average4.4 bag3%₦12,000₦54,384
MaterialSharp sand, per tonne0.74 tonne8%₦6,500₦5,195
MaterialGranite 3/4", per tonne1.39 tonne5%₦18,000₦26,271
MaterialWater, per m30.18 m³-₦3,500₦630
Plant (days)Concrete mixer, 1-bag (petrol)0.06667 day-₦43,546₦2,903
Labour (hours)Mason / bricklayer1 h-₦2,456₦2,456
Labour (hours)Unskilled labourer6 h-₦1,146₦6,878
Materials₦86,480
Labour₦9,334
Plant₦2,903
Net unit rate per m³₦98,716

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m³Tender rate incl. OH&P and VAT
Abuja (FCT)₦98,716₦131,761
Lagos₦104,797₦139,877
Port Harcourt₦105,400₦140,683
Ibadan₦92,380₦123,305
Osogbo (Osun)₦92,837₦123,913
Kano₦90,184₦120,373
Kaduna₦91,329₦121,901
Enugu₦95,062₦126,884
Benin City₦96,171₦128,365
Uyo₦99,998₦133,472
Jos₦92,252₦123,133
Riverine / creek site₦126,755₦169,186

Related concrete rates

Frequently asked questions

How much does plain concrete 1:3:6 in blinding (site-mixed) cost per m³ in Nigeria?

About ₦98,716 per m³ net in Abuja as at 15 October 2026, or about ₦131,761 per m³ as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦104,797 per m³ and the tender rate about ₦139,877 per m³.

What does the rate include?

Materials (Granite 3/4", OPC 42.5 cement, Sharp sand, Water) with waste allowances; labour (Mason / bricklayer, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Concrete mixer, 1-bag (petrol)) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/b01-plain-concrete-1-3-6-in-blinding-site-mixed/, prices as at 15 October 2026.