BuildocratRate Book

Prices as at 15 October 2026, checked weekly. Base location Abuja.

Ready-mix C25/30 placed by pump in suspended slab: cost per m³ in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦181,224per m³

Tender rate about ₦241,888 per m³ with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for ready-mix C25/30 placed by pump in suspended slab is ₦181,224 per m³ in Abuja: ₦175,900 materials, ₦4,831 labour and ₦493 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦241,888 per m³.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialReady-mix C25/30, delivered Abuja (ex-pump)1 m³2%₦165,000₦168,300
MaterialConcrete pump hire, per pour (<=60 m3)0.02 pour-₦380,000₦7,600
Plant (days)Poker vibrator (petrol)0.025 day-₦19,728₦493
Labour (hours)Mason / bricklayer0.8 h-₦2,456₦1,965
Labour (hours)Unskilled labourer2.5 h-₦1,146₦2,866
Materials₦175,900
Labour₦4,831
Plant₦493
Net unit rate per m³₦181,224

Scope note: Small pours cost much more.

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per m³Tender rate incl. OH&P and VAT
Abuja (FCT)₦181,224₦241,888
Lagos₦192,189₦256,524
Port Harcourt₦195,094₦260,401
Ibadan₦171,438₦228,826
Osogbo (Osun)₦172,965₦230,865
Kano₦167,678₦223,808
Kaduna₦169,582₦226,350
Enugu₦176,730₦235,890
Benin City₦178,595₦238,380
Uyo₦185,791₦247,984
Jos₦171,351₦228,711
Riverine / creek site₦234,674₦313,231

Related concrete rates

Frequently asked questions

How much does ready-mix C25/30 placed by pump in suspended slab cost per m³ in Nigeria?

About ₦181,224 per m³ net in Abuja as at 15 October 2026, or about ₦241,888 per m³ as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦192,189 per m³ and the tender rate about ₦256,524 per m³.

What does the rate include?

Materials (Concrete pump hire, Ready-mix C25/30) with waste allowances; labour (Mason / bricklayer, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Poker vibrator (petrol)) including fuel and operator. Overheads, profit and VAT are excluded from the net rate. Scope note: Small pours cost much more.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/b05-ready-mix-c25-30-placed-by-pump-in-suspended-slab/, prices as at 15 October 2026.