As at 15 October 2026, Buildocrat estimates a 50kg bag of cement at about ₦12,360 in Uyo, a mason at about ₦12,750 a day, and 225mm blockwork at about ₦12,862 per m² net. Rates for Uyo apply location factors to the Abuja base: materials 1.03, labour 0.85, plant 1.03.

Key material prices in Uyo

MaterialUnitEstimated price
OPC 42.5 cement, 50kg bag - adopted market averagebag₦12,360
High-yield rebar 12-16mm, per tonnetonne₦1,081,500
9" (225mm) hollow sandcrete blockunit₦876
Sharp sand, 20t tipper loadload₦133,900
Granite 3/4", 30t loadload₦556,200
Aluminium longspan 0.55mm, Grade A (market)m²₦8,343
Floor tile 600x600 ceramic/porcelain, mid-rangem²₦8,755
Emulsion paint, standard, 20L20L pail₦51,500
2"x4"x12' hardwood (Gmelina/Akpontu)length₦4,944
Diesel (AGO), pump price, per litrelitre₦1,926
Polyethylene water tank 2,000Lunit₦267,800
Hybrid inverter 5kVA/48Vunit₦515,000
Ready-mix C25/30, delivered Abuja (ex-pump)m³₦169,950
2.5mm2 single-core Cu cable, 100m coil100m coil₦79,310
Aluminium casement window, 5mm glass & net - supply & fixm²₦97,850
API 5L X52 line pipe 12" (323.9x9.53mm, 73.9 kg/m), bare, per mm₦142,011
Sheet pile PU18 (128 kg/m2 of wall), per m2m²₦209,134
HDPE PE100 SDR17 (PN10) pipe 110mm (2.02 kg/m), per mm₦8,740
33kV 1-core 240mm2 Cu XLPE/SWA cable, per mm₦54,590
Dry powder extinguisher 9kgunit₦46,350
Wheelbarrow heavy dutyunit₦66,950
Armour rock 3-6t, delivered to site, per tonnetonne₦39,140
Excavator 20-22t (CAT 320D/320GC), foreign usedunit₦175,100,000
Bulldozer D6 class (CAT D6H/D6R), foreign usedunit₦206,000,000
Motor grader CAT 140G, Nigerian usedunit₦82,400,000
Tipper truck 6x4 371hp 30t (Sinotruk Howo), newunit₦103,000,000
Truck crane 50-55t (SANY/XCMG), foreign usedunit₦144,200,000
Diesel generator 100kVA soundproof (Mikano), newunit₦18,540,000
Concrete batching plant 50 m3/h, newunit₦175,100,000
Block moulding line FT4-5 / mobile type (~3,000 blocks/day)unit₦5,356,000
Crushing plant 200 t/h (jaw + cone + screens), Nigerian usedunit₦180,250,000
Suction dredger 10-12", Nigerian usedunit₦46,350,000
Rotary bored-pile rig 150-200kNm (SANY SR150/Bauer BG), foreign usedunit₦463,500,000
Total station 2" (Leica/Sokkia/Topcon), newunit₦17,299,674

Labour rates in Uyo

TradeDaily wageAll-in day
Mason / bricklayer₦12,750₦16,702
Unskilled labourer₦5,950₦7,794
Carpenter (formwork & roof)₦14,450₦18,930
Iron bender / steel fixer₦12,750₦16,702
Electrician₦15,725₦20,600
Plumber₦14,450₦18,930
Tiler₦12,750₦16,702
Painter₦10,625₦13,919
Plasterer / screeder₦11,475₦15,032
Welder / fabricator₦15,300₦20,043

Common BoQ rates in Uyo

ItemUnitNet rateTender rate
225mm hollow sandcrete blockwork in cement-sand mortar 1:6m²₦12,862₦17,167
150mm hollow sandcrete blockwork in cement-sand mortar 1:6m²₦10,316₦13,770
Reinforced concrete 1:2:4 in foundations / bases / ground beamsm³₦129,241₦172,504
Reinforced concrete 1:2:4 in suspended slabs, beams & columnsm³₦136,312₦181,942
High-yield reinforcement 12-16mm, cut, bent & fixedtonne₦1,229,827₦1,641,508
Formwork (marine board) to soffit of suspended slab incl. propping n.e. 3.5mm²₦10,738₦14,332
Formwork (marine board) to columns and beamsm²₦10,325₦13,781
15mm internal plaster, cement-sand 1:6, to blockworkm²₦2,977₦3,973
20mm external render, cement-sand 1:4m²₦4,448₦5,937
40mm cement-sand 1:3 floor screedm²₦6,257₦8,352
600x600 ceramic floor tiles (mid-range) on adhesive, groutedm²₦13,931₦18,594
Skim coat + 3 coats emulsion to internal plastered wallsm²₦2,307₦3,079
2 coats weathershield paint to external renderm²₦1,549₦2,068
Timber roof: 2x4 trusses/rafters, 2x3 purlins, 2x6 wall plate, treated (slope area)m²₦8,628₦11,516
0.55mm longspan aluminium (Grade A) on timber purlins incl. laps, ridges & fixingsm²₦10,972₦14,645
Stone-coated steel tiles on 2x2 battens incl. fixingsm²₦16,577₦22,126
Aluminium casement window, 5mm glass & net, s&f incl. making goodm²₦98,731₦131,781
Lighting point: 1.5mm2 in 20mm conduit (avg 8m), switch share, LED downlightpoint₦29,116₦38,863
13A socket point: 2.5mm2 in 20mm conduit (avg 10m), twin socketpoint₦39,617₦52,879
Asphalt wearing course 50mm, laid & compactedm²₦21,085₦28,143
60mm interlocking paving on 50mm sand bed, compactedm²₦11,246₦15,011
225mm block fence wall 2.4m high incl. foundation, piers, plaster both sides & razor wirem₦82,463₦110,067

Location factors are starting points based on market evidence and judgement; confirm with local quotes. How the factors work.

Frequently asked questions

How much is cement in Uyo?

About ₦12,360 per 50kg bag (Buildocrat estimate, 15 October 2026).

How much is a mason paid per day in Uyo?

About ₦12,750 a day, or ₦16,702 all-in.

How much does blockwork cost per square metre in Uyo?

225mm hollow sandcrete blockwork is about ₦12,862 per m² net, or ₦17,167 including overheads, profit and VAT.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/locations/uyo/, prices as at 15 October 2026.