Bored cast-in-place pile 900mm dia in C30/37 concrete incl. rebar cage and drilling fluid: cost per m in Nigeria
Net unit rate in Abuja, excluding overheads, profit and VAT
₦432,519per m
Tender rate about ₦577,304 per m with overheads, contingency, profit and VAT.
Price a BoQ with this rateAs at 15 October 2026, the net unit rate for bored cast-in-place pile 900mm dia in C30/37 concrete incl. rebar cage and drilling fluid is ₦432,519 per m in Abuja: ₦220,353 materials, ₦13,018 labour and ₦199,148 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦577,304 per m.
Rate build-up (Abuja, Oct 2026)
| Resource type | Resource | Quantity per unit | Waste | Rate | Cost |
|---|---|---|---|---|---|
| Material | Ready-mix C30/37, delivered Abuja (ex-pump) | 0.7 m³ | 2% | ₦178,000 | ₦127,092 |
| Material | High-yield rebar 12-16mm, per tonne | 0.07 tonne | 5% | ₦1,050,000 | ₦77,175 |
| Material | Binding wire, per kg | 0.8 kg | 5% | ₦1,900 | ₦1,596 |
| Material | Bentonite (API grade), per tonne | 0.03 tonne | 5% | ₦460,000 | ₦14,490 |
| Plant (days) | Bored piling rig (600-900mm) | 0.04546 day | - | ₦3,449,850 | ₦156,813 |
| Plant (days) | Mobile crane 25t | 0.04546 day | - | ₦749,240 | ₦34,057 |
| Plant (days) | Hydraulic excavator 20-22t (CAT 320/215 class) | 0.01 day | - | ₦827,850 | ₦8,278 |
| Labour (hours) | Piling hand | 3 h | - | ₦1,965 | ₦5,895 |
| Labour (hours) | Iron bender / steel fixer | 2.2 h | - | ₦2,456 | ₦5,404 |
| Labour (hours) | Unskilled labourer | 1.5 h | - | ₦1,146 | ₦1,719 |
| Materials | ₦220,353 | ||||
| Labour | ₦13,018 | ||||
| Plant | ₦199,148 | ||||
| Net unit rate per m | ₦432,519 |
Scope note: Rig mobilisation, testing and pile-head cut-off measured separately.
Rate by location
Materials, labour and plant are adjusted separately with Buildocrat's location factors.
| Location | Net rate per m | Tender rate incl. OH&P and VAT |
|---|---|---|
| Abuja (FCT) | ₦432,519 | ₦577,304 |
| Lagos | ₦456,739 | ₦609,631 |
| Port Harcourt | ₦465,428 | ₦621,229 |
| Ibadan | ₦408,941 | ₦545,832 |
| Osogbo (Osun) | ₦414,476 | ₦553,221 |
| Kano | ₦403,883 | ₦539,081 |
| Kaduna | ₦406,477 | ₦542,543 |
| Enugu | ₦421,526 | ₦562,630 |
| Benin City | ₦427,972 | ₦571,235 |
| Uyo | ₦443,152 | ₦591,495 |
| Jos | ₦412,663 | ₦550,801 |
| Riverine / creek site | ₦579,586 | ₦773,601 |
Related piling & ground engineering rates
- P01 Bored cast-in-place pile 600mm dia in C30/37 concrete incl. rebar cage and drilling fluid₦236,611 per m
- P03 Bored cast-in-place pile 1200mm dia in C30/37 concrete incl. rebar cage and drilling fluid₦682,733 per m
- P04 Precast concrete pile 400x400mm supplied and driven₦173,478 per m
- P05 Steel tubular pile 762x14mm supplied and driven incl. splices₦533,280 per m
- P06 Steel sheet piling PU18, permanent, supplied and driven by vibro hammer₦227,190 per m²
- P07 Temporary sheet piling PU18 driven and extracted (30% material write-off/hire)₦86,008 per m²
- P08 Break down pile head 600mm and prepare starter bars₦32,488 per unit
- P09 Pile integrity test (low-strain), per pile₦30,000 per unit
- P10 Prefabricated vertical drains installed to 15m₦662 per m
- P11 Gabion box 2x1x1m filled with hand-packed stone₦103,028 per unit
- P12 Reno mattress 0.3m filled with stone₦20,033 per m²
- P13 Biaxial geogrid laid in fill₦3,434 per m²
- P14 HDPE geomembrane 1.5mm laid and welded (lining)₦8,418 per m²
- P15 Soil nail 25mm x 6m, drilled and grouted, with head plate₦109,737 per unit
- P16 Ground/rock anchor 32mm bar, drilled and grouted₦42,294 per m
- P17 Geosynthetic clay liner laid with overlaps₦9,976 per m²
- P18 Settlement plate installed and initial reading₦103,668 per unit
- P19 Non-woven geotextile 400g/m2 laid as separator/filter₦2,696 per m²
Frequently asked questions
How much does bored cast-in-place pile 900mm dia in C30/37 concrete incl. rebar cage and drilling fluid cost per m in Nigeria?
About ₦432,519 per m net in Abuja as at 15 October 2026, or about ₦577,304 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).
What is the rate in Lagos?
Applying Buildocrat's Lagos location factors, the net rate is about ₦456,739 per m and the tender rate about ₦609,631 per m.
What does the rate include?
Materials (Bentonite (API grade), Binding wire, High-yield rebar 12-16mm, Ready-mix C30/37) with waste allowances; labour (Iron bender / steel fixer, Piling hand, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Bored piling rig (600-900mm), Hydraulic excavator 20-22t (CAT 320/215 class), Mobile crane 25t) including fuel and operator. Overheads, profit and VAT are excluded from the net rate. Scope note: Rig mobilisation, testing and pile-head cut-off measured separately.
How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/p02-bored-cast-in-place-pile-900mm-dia-in-c30-37-concrete-in/, prices as at 15 October 2026.