Bored cast-in-place pile 900mm dia in C30/37 concrete incl. rebar cage and drilling fluid: cost per m in Nigeria

Net unit rate in Abuja, excluding overheads, profit and VAT

₦432,519per m

Tender rate about ₦577,304 per m with overheads, contingency, profit and VAT.

Price a BoQ with this rate

As at 15 October 2026, the net unit rate for bored cast-in-place pile 900mm dia in C30/37 concrete incl. rebar cage and drilling fluid is ₦432,519 per m in Abuja: ₦220,353 materials, ₦13,018 labour and ₦199,148 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦577,304 per m.

Rate build-up (Abuja, Oct 2026)

Resource typeResourceQuantity per unitWasteRateCost
MaterialReady-mix C30/37, delivered Abuja (ex-pump)0.7 m³2%₦178,000₦127,092
MaterialHigh-yield rebar 12-16mm, per tonne0.07 tonne5%₦1,050,000₦77,175
MaterialBinding wire, per kg0.8 kg5%₦1,900₦1,596
MaterialBentonite (API grade), per tonne0.03 tonne5%₦460,000₦14,490
Plant (days)Bored piling rig (600-900mm)0.04546 day-₦3,449,850₦156,813
Plant (days)Mobile crane 25t0.04546 day-₦749,240₦34,057
Plant (days)Hydraulic excavator 20-22t (CAT 320/215 class)0.01 day-₦827,850₦8,278
Labour (hours)Piling hand3 h-₦1,965₦5,895
Labour (hours)Iron bender / steel fixer2.2 h-₦2,456₦5,404
Labour (hours)Unskilled labourer1.5 h-₦1,146₦1,719
Materials₦220,353
Labour₦13,018
Plant₦199,148
Net unit rate per m₦432,519

Scope note: Rig mobilisation, testing and pile-head cut-off measured separately.

Rate by location

Materials, labour and plant are adjusted separately with Buildocrat's location factors.

LocationNet rate per mTender rate incl. OH&P and VAT
Abuja (FCT)₦432,519₦577,304
Lagos₦456,739₦609,631
Port Harcourt₦465,428₦621,229
Ibadan₦408,941₦545,832
Osogbo (Osun)₦414,476₦553,221
Kano₦403,883₦539,081
Kaduna₦406,477₦542,543
Enugu₦421,526₦562,630
Benin City₦427,972₦571,235
Uyo₦443,152₦591,495
Jos₦412,663₦550,801
Riverine / creek site₦579,586₦773,601

Related piling & ground engineering rates

Frequently asked questions

How much does bored cast-in-place pile 900mm dia in C30/37 concrete incl. rebar cage and drilling fluid cost per m in Nigeria?

About ₦432,519 per m net in Abuja as at 15 October 2026, or about ₦577,304 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).

What is the rate in Lagos?

Applying Buildocrat's Lagos location factors, the net rate is about ₦456,739 per m and the tender rate about ₦609,631 per m.

What does the rate include?

Materials (Bentonite (API grade), Binding wire, High-yield rebar 12-16mm, Ready-mix C30/37) with waste allowances; labour (Iron bender / steel fixer, Piling hand, Unskilled labourer) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Bored piling rig (600-900mm), Hydraulic excavator 20-22t (CAT 320/215 class), Mobile crane 25t) including fuel and operator. Overheads, profit and VAT are excluded from the net rate. Scope note: Rig mobilisation, testing and pile-head cut-off measured separately.

How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/p02-bored-cast-in-place-pile-900mm-dia-in-c30-37-concrete-in/, prices as at 15 October 2026.