Steel tubular pile 762x14mm supplied and driven incl. splices: cost per m in Nigeria
Net unit rate in Abuja, excluding overheads, profit and VAT
₦533,280per m
Tender rate about ₦711,794 per m with overheads, contingency, profit and VAT.
Price a BoQ with this rateAs at 15 October 2026, the net unit rate for steel tubular pile 762x14mm supplied and driven incl. splices is ₦533,280 per m in Abuja: ₦499,259 materials, ₦2,260 labour and ₦31,761 plant. With overheads (7.5%), contingency (5%), profit (10%) and VAT (7.5%) the tender rate is about ₦711,794 per m.
Rate build-up (Abuja, Oct 2026)
| Resource type | Resource | Quantity per unit | Waste | Rate | Cost |
|---|---|---|---|---|---|
| Material | Steel tubular pile 762x14mm (258 kg/m), per m | 1 m | 3% | ₦481,927 | ₦496,385 |
| Material | Low-hydrogen electrode E7018, per kg | 0.4 kg | 10% | ₦6,532 | ₦2,874 |
| Plant (days) | Piling rig with diesel/hydraulic impact hammer (crawler) | 0.02 day | - | ₦1,588,070 | ₦31,761 |
| Labour (hours) | Piling hand | 0.7 h | - | ₦1,965 | ₦1,376 |
| Labour (hours) | Welder / fabricator | 0.3 h | - | ₦2,948 | ₦884 |
| Materials | ₦499,259 | ||||
| Labour | ₦2,260 | ||||
| Plant | ₦31,761 | ||||
| Net unit rate per m | ₦533,280 |
Rate by location
Materials, labour and plant are adjusted separately with Buildocrat's location factors.
| Location | Net rate per m | Tender rate incl. OH&P and VAT |
|---|---|---|
| Abuja (FCT) | ₦533,280 | ₦711,794 |
| Lagos | ₦565,005 | ₦754,138 |
| Port Harcourt | ₦575,649 | ₦768,346 |
| Ibadan | ₦506,277 | ₦675,752 |
| Osogbo (Osun) | ₦511,792 | ₦683,113 |
| Kano | ₦496,179 | ₦662,274 |
| Kaduna | ₦501,240 | ₦669,028 |
| Enugu | ₦522,208 | ₦697,016 |
| Benin City | ₦527,881 | ₦704,588 |
| Uyo | ₦548,872 | ₦732,605 |
| Jos | ₦506,867 | ₦676,540 |
| Riverine / creek site | ₦695,989 | ₦928,969 |
Related piling & ground engineering rates
- P01 Bored cast-in-place pile 600mm dia in C30/37 concrete incl. rebar cage and drilling fluid₦236,611 per m
- P02 Bored cast-in-place pile 900mm dia in C30/37 concrete incl. rebar cage and drilling fluid₦432,519 per m
- P03 Bored cast-in-place pile 1200mm dia in C30/37 concrete incl. rebar cage and drilling fluid₦682,733 per m
- P04 Precast concrete pile 400x400mm supplied and driven₦173,478 per m
- P06 Steel sheet piling PU18, permanent, supplied and driven by vibro hammer₦227,190 per m²
- P07 Temporary sheet piling PU18 driven and extracted (30% material write-off/hire)₦86,008 per m²
- P08 Break down pile head 600mm and prepare starter bars₦32,488 per unit
- P09 Pile integrity test (low-strain), per pile₦30,000 per unit
- P10 Prefabricated vertical drains installed to 15m₦662 per m
- P11 Gabion box 2x1x1m filled with hand-packed stone₦103,028 per unit
- P12 Reno mattress 0.3m filled with stone₦20,033 per m²
- P13 Biaxial geogrid laid in fill₦3,434 per m²
- P14 HDPE geomembrane 1.5mm laid and welded (lining)₦8,418 per m²
- P15 Soil nail 25mm x 6m, drilled and grouted, with head plate₦109,737 per unit
- P16 Ground/rock anchor 32mm bar, drilled and grouted₦42,294 per m
- P17 Geosynthetic clay liner laid with overlaps₦9,976 per m²
- P18 Settlement plate installed and initial reading₦103,668 per unit
- P19 Non-woven geotextile 400g/m2 laid as separator/filter₦2,696 per m²
Frequently asked questions
How much does steel tubular pile 762x14mm supplied and driven incl. splices cost per m in Nigeria?
About ₦533,280 per m net in Abuja as at 15 October 2026, or about ₦711,794 per m as a tender rate including overheads, contingency, profit and VAT (Buildocrat Nigeria Construction Rate Book).
What is the rate in Lagos?
Applying Buildocrat's Lagos location factors, the net rate is about ₦565,005 per m and the tender rate about ₦754,138 per m.
What does the rate include?
Materials (Low-hydrogen electrode E7018, Steel tubular pile 762x14mm (258 kg/m)) with waste allowances; labour (Piling hand, Welder / fabricator) at all-in rates including feeding, transport, idle time and statutory costs; and plant (Piling rig with diesel/hydraulic impact hammer (crawler)) including fuel and operator. Overheads, profit and VAT are excluded from the net rate.
How to cite: Buildocrat, Nigeria Construction Rate Book, https://rates.buildocrat.store/rates/p05-steel-tubular-pile-762x14mm-supplied-and-driven-incl-spl/, prices as at 15 October 2026.